    <title>question Recalculate Estimate at Completion and Estimate to Complete in SPM in Community Central forum</title>
    <link>https://www.servicenow.com/community/community-central-forum/recalculate-estimate-at-completion-and-estimate-to-complete-in/m-p/3503807#M6293</link>
    <description>&lt;DIV&gt;&lt;P&gt;Hi Community,&lt;/P&gt;&lt;P&gt;In an SPM implementation, our client wants &lt;STRONG&gt;Estimate to Complete(ETC) and Estimate at Completion(EAC)&lt;/STRONG&gt; to be recalculated &lt;STRONG&gt;based on Planned Value only up to the 15th of the next month &lt;/STRONG&gt;because they received the A&lt;STRONG&gt;ctuals&lt;/STRONG&gt; by mid of next month, but they do &lt;STRONG&gt;not&lt;/STRONG&gt; want to modify the standard fiscal periods.&lt;/P&gt;&lt;P&gt;Has anyone implemented something similar?&lt;/P&gt;&lt;P&gt;Looking for guidance on:&lt;/P&gt;&lt;UL&gt;&lt;LI&gt;Whether any OOTB capability supports this.&lt;/LI&gt;&lt;LI&gt;Recommended customization approach (if required).&lt;/LI&gt;&lt;LI&gt;Any known impacts to project financials or EV calculations.&lt;/LI&gt;&lt;/UL&gt;&lt;P&gt;Thanks for your inputs!&lt;/P&gt;&lt;/DIV&gt;</description>
    <pubDate>Mon, 09 Mar 2026 06:55:47 GMT</pubDate>
    <dc:creator>MohitC600613157</dc:creator>
    <dc:date>2026-03-09T06:55:47Z</dc:date>
    <item>
      <title>Recalculate Estimate at Completion and Estimate to Complete in SPM</title>
      <link>https://www.servicenow.com/community/community-central-forum/recalculate-estimate-at-completion-and-estimate-to-complete-in/m-p/3503807#M6293</link>
      <description>&lt;DIV&gt;&lt;P&gt;Hi Community,&lt;/P&gt;&lt;P&gt;In an SPM implementation, our client wants &lt;STRONG&gt;Estimate to Complete(ETC) and Estimate at Completion(EAC)&lt;/STRONG&gt; to be recalculated &lt;STRONG&gt;based on Planned Value only up to the 15th of the next month &lt;/STRONG&gt;because they received the A&lt;STRONG&gt;ctuals&lt;/STRONG&gt; by mid of next month, but they do &lt;STRONG&gt;not&lt;/STRONG&gt; want to modify the standard fiscal periods.&lt;/P&gt;&lt;P&gt;Has anyone implemented something similar?&lt;/P&gt;&lt;P&gt;Looking for guidance on:&lt;/P&gt;&lt;UL&gt;&lt;LI&gt;Whether any OOTB capability supports this.&lt;/LI&gt;&lt;LI&gt;Recommended customization approach (if required).&lt;/LI&gt;&lt;LI&gt;Any known impacts to project financials or EV calculations.&lt;/LI&gt;&lt;/UL&gt;&lt;P&gt;Thanks for your inputs!&lt;/P&gt;&lt;/DIV&gt;</description>
      <pubDate>Mon, 09 Mar 2026 06:55:47 GMT</pubDate>
      <guid>https://www.servicenow.com/community/community-central-forum/recalculate-estimate-at-completion-and-estimate-to-complete-in/m-p/3503807#M6293</guid>
      <dc:creator>MohitC600613157</dc:creator>
      <dc:date>2026-03-09T06:55:47Z</dc:date>