    <title>question Re: Can we calculate the variance (days) between project task and the baseline date in SPM forum</title>
    <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034363#M29961</link>
    <description>&lt;P&gt;Hi&amp;nbsp;&lt;A href="https://www.servicenow.com/community/community?id=community_user_profile&amp;amp;user=d79cd118db711b80fc5b7a9e0f961918" rel="nofollow"&gt;Andrew&lt;/A&gt;,&lt;/P&gt;
&lt;P&gt;I would suggest to look at the functionality on the financial baseline and create the same(+) for schedule baseline. On the Financial Baseline the baseline values are compared with the Current.&lt;/P&gt;
&lt;P&gt;&lt;span class="lia-inline-image-display-wrapper" image-alt="find_real_file.png"&gt;&lt;img src="https://www.servicenow.com/community/image/serverpage/image-id/103994i488B704EA989C65A/image-size/large?v=v2&amp;amp;px=999" role="button" title="find_real_file.png" alt="find_real_file.png" /&gt;&lt;/span&gt;&lt;/P&gt;
&lt;P&gt;You could do the same for scheduled baselines and add two new fields - one for "Actual end date" and one like "End date varians". &amp;nbsp;Then create a functionality to calculate the varians after the baseline is created - I think it could solve your challenge. I would recommend to execute the calculations on the schedule baseline table.&lt;/P&gt;
&lt;P&gt;&lt;span class="lia-inline-image-display-wrapper" image-alt="find_real_file.png"&gt;&lt;img src="https://www.servicenow.com/community/image/serverpage/image-id/104001i5AA6A38A3A510BED/image-size/large?v=v2&amp;amp;px=999" role="button" title="find_real_file.png" alt="find_real_file.png" /&gt;&lt;/span&gt;&lt;/P&gt;
&lt;P&gt;Hope this helps you&lt;/P&gt;
&lt;P&gt;Brian&amp;nbsp;&lt;/P&gt;</description>
    <pubDate>Mon, 08 Oct 2018 13:53:18 GMT</pubDate>
    <dc:creator>Brian Gadeberg</dc:creator>
    <dc:date>2018-10-08T13:53:18Z</dc:date>
    <item>
      <title>Can we calculate the variance (days) between project task and the baseline date</title>
      <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034362#M29960</link>
      <description>&lt;P&gt;Hi,&lt;/P&gt;
&lt;P&gt;We want to be able to report on the variance between the baseline value for say Finish date and the task planned finish date.&lt;/P&gt;
&lt;P&gt;I have built a report using the planned_task_baseline_item. &amp;nbsp;This report lists the two fields I want, now I want to calculate the variance.&lt;/P&gt;
&lt;P&gt;Could I create a database view, can you add a calculated type field to a database view?&lt;/P&gt;
&lt;P&gt;Any ideas?&lt;/P&gt;
&lt;P&gt;Tx&lt;/P&gt;
&lt;P&gt;Andrew Payze&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;</description>
      <pubDate>Wed, 19 Sep 2018 15:25:49 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034362#M29960</guid>
      <dc:creator>Andrew Payze</dc:creator>
      <dc:date>2018-09-19T15:25:49Z</dc:date>
    </item>
    <item>
      <title>Re: Can we calculate the variance (days) between project task and the baseline date</title>
      <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034363#M29961</link>
      <description>&lt;P&gt;Hi&amp;nbsp;&lt;A href="https://www.servicenow.com/community/community?id=community_user_profile&amp;amp;user=d79cd118db711b80fc5b7a9e0f961918" rel="nofollow"&gt;Andrew&lt;/A&gt;,&lt;/P&gt;
&lt;P&gt;I would suggest to look at the functionality on the financial baseline and create the same(+) for schedule baseline. On the Financial Baseline the baseline values are compared with the Current.&lt;/P&gt;
&lt;P&gt;&lt;span class="lia-inline-image-display-wrapper" image-alt="find_real_file.png"&gt;&lt;img src="https://www.servicenow.com/community/image/serverpage/image-id/103994i488B704EA989C65A/image-size/large?v=v2&amp;amp;px=999" role="button" title="find_real_file.png" alt="find_real_file.png" /&gt;&lt;/span&gt;&lt;/P&gt;
&lt;P&gt;You could do the same for scheduled baselines and add two new fields - one for "Actual end date" and one like "End date varians". &amp;nbsp;Then create a functionality to calculate the varians after the baseline is created - I think it could solve your challenge. I would recommend to execute the calculations on the schedule baseline table.&lt;/P&gt;
&lt;P&gt;&lt;span class="lia-inline-image-display-wrapper" image-alt="find_real_file.png"&gt;&lt;img src="https://www.servicenow.com/community/image/serverpage/image-id/104001i5AA6A38A3A510BED/image-size/large?v=v2&amp;amp;px=999" role="button" title="find_real_file.png" alt="find_real_file.png" /&gt;&lt;/span&gt;&lt;/P&gt;
&lt;P&gt;Hope this helps you&lt;/P&gt;
&lt;P&gt;Brian&amp;nbsp;&lt;/P&gt;</description>
      <pubDate>Mon, 08 Oct 2018 13:53:18 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034363#M29961</guid>
      <dc:creator>Brian Gadeberg</dc:creator>
      <dc:date>2018-10-08T13:53:18Z</dc:date>
    </item>
    <item>
      <title>Re: Can we calculate the variance (days) between project task and the baseline date</title>
      <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034364#M29962</link>
      <description>&lt;P&gt;Hi Brian,&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;Thanks for this … will taker a looks at the Financial Baseline.&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;I assume when you are referring to "Create a functionality". this would be a script?&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;Regards and thanks&lt;/P&gt;
&lt;P&gt;Andrew&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;
&lt;P&gt;&amp;nbsp;&lt;/P&gt;</description>
      <pubDate>Mon, 08 Oct 2018 19:17:32 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034364#M29962</guid>
      <dc:creator>Andrew Payze</dc:creator>
      <dc:date>2018-10-08T19:17:32Z</dc:date>
    </item>
    <item>
      <title>Re: Can we calculate the variance (days) between project task and the baseline date</title>
      <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034365#M29963</link>
      <description>&lt;P&gt;Yes &lt;span class="lia-unicode-emoji" title=":slightly_smiling_face:"&gt;🙂&lt;/span&gt;&lt;/P&gt;</description>
      <pubDate>Mon, 08 Oct 2018 19:33:02 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034365#M29963</guid>
      <dc:creator>Brian Gadeberg</dc:creator>
      <dc:date>2018-10-08T19:33:02Z</dc:date>
    </item>
    <item>
      <title>Re: Can we calculate the variance (days) between project task and the baseline date</title>
      <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034366#M29964</link>
      <description>&lt;P&gt;I noticed that actuals benefits, for example, are not considered OOTB, which is strange.&lt;/P&gt;
&lt;P&gt;I created the field in the baseline table and completed the mapping/configuration and now it's perfectly stored ... however doing a compare still shows the field empty no matter what &lt;span class="lia-unicode-emoji" title=":disappointed_face:"&gt;😞&lt;/span&gt;&lt;/P&gt;</description>
      <pubDate>Thu, 24 Jun 2021 10:45:06 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034366#M29964</guid>
      <dc:creator>edo88</dc:creator>
      <dc:date>2021-06-24T10:45:06Z</dc:date>
    </item>
    <item>
      <title>Re: Can we calculate the variance (days) between project task and the baseline date</title>
      <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034367#M29965</link>
      <description>&lt;P&gt;I noticed the problem is the prefix "u_", you can bypass that using this:&lt;/P&gt;
&lt;P&gt;https://community.servicenow.com/community?id=community_question&amp;amp;sys_id=432ec3eddb9cdbc01dcaf3231f96196c&lt;/P&gt;</description>
      <pubDate>Thu, 24 Jun 2021 11:06:55 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034367#M29965</guid>
      <dc:creator>edo88</dc:creator>
      <dc:date>2021-06-24T11:06:55Z</dc:date>
    </item>
    <item>
      <title>Re: Can we calculate the variance (days) between project task and the baseline date</title>
      <link>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034368#M29966</link>
      <description>&lt;P&gt;&lt;SN-MENTION class="sn-mention" table="live_profile" sysid="736f0a69db181fc09c9ffb651f9619e8"&gt;@edo88&lt;/SN-MENTION&gt;&amp;nbsp;how did you create your variance report? can you help me with&amp;nbsp;that please?&amp;nbsp;&lt;/P&gt;</description>
      <pubDate>Mon, 25 Apr 2022 21:20:44 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/can-we-calculate-the-variance-days-between-project-task-and-the/m-p/1034368#M29966</guid>
      <dc:creator>Taha_Alawadhi</dc:creator>
      <dc:date>2022-04-25T21:20:44Z</dc:date>