    <title>question Re: total planned cost on resource_plan and cost_plan is different and i want to make it similar in SPM forum</title>
    <link>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3294279#M47530</link>
    <description>&lt;P&gt;Hi,&lt;/P&gt;
&lt;P&gt;If you have used "rate override" and "resource rate" in resource plan, it should override the system default of 50$. If it is not, please raise a case with us and we will look into it.&lt;/P&gt;</description>
    <pubDate>Fri, 20 Jun 2025 04:44:18 GMT</pubDate>
    <dc:creator>Arnab19</dc:creator>
    <dc:date>2025-06-20T04:44:18Z</dc:date>
    <item>
      <title>total planned cost on resource_plan and cost_plan is different and i want to make it similar</title>
      <link>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3293510#M47511</link>
      <description>&lt;P&gt;on resource plan if the bill rate :200 and the planned hours are 85 then it is showing planned billed amount as 17000(85*200). but on the related list cost_plan associated to this resource_plan, the total planned cost is 4250(allocated hours 85 * default system rate 50). but because they is already a bill rate being captured on resource_plan table i want the same to reflect on cost_plan table too. can someone pls guide me with this configuration.&lt;/P&gt;</description>
      <pubDate>Thu, 19 Jun 2025 09:15:30 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3293510#M47511</guid>
      <dc:creator>tejender</dc:creator>
      <dc:date>2025-06-19T09:15:30Z</dc:date>
    </item>
    <item>
      <title>Re: total planned cost on resource_plan and cost_plan is different and i want to make it similar</title>
      <link>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3294279#M47530</link>
      <description>&lt;P&gt;Hi,&lt;/P&gt;
&lt;P&gt;If you have used "rate override" and "resource rate" in resource plan, it should override the system default of 50$. If it is not, please raise a case with us and we will look into it.&lt;/P&gt;</description>
      <pubDate>Fri, 20 Jun 2025 04:44:18 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3294279#M47530</guid>
      <dc:creator>Arnab19</dc:creator>
      <dc:date>2025-06-20T04:44:18Z</dc:date>
    </item>
    <item>
      <title>Re: total planned cost on resource_plan and cost_plan is different and i want to make it similar</title>
      <link>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3296415#M47561</link>
      <description>&lt;P&gt;Hi,&lt;BR /&gt;So when i have a rate override chacked and bill rate is mentioned, the resource plan -total planned cost is 0 as well as the cost plan-total planned cost is 0 even though the resource rate is mentioned&amp;nbsp;&lt;BR /&gt;&lt;BR /&gt;&lt;BR /&gt;&lt;BR /&gt;Do we have to raise a case for this as this is unexpected behaviour&lt;/P&gt;</description>
      <pubDate>Mon, 23 Jun 2025 10:11:53 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3296415#M47561</guid>
      <dc:creator>tejender</dc:creator>
      <dc:date>2025-06-23T10:11:53Z</dc:date>
    </item>
    <item>
      <title>Re: total planned cost on resource_plan and cost_plan is different and i want to make it similar</title>
      <link>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3296543#M47562</link>
      <description>&lt;P&gt;&lt;SPAN&gt;Hi Arnab,&lt;/SPAN&gt;&lt;BR /&gt;&lt;SPAN&gt;So when i have a rate override chacked and bill rate is mentioned, the resource plan -total planned cost is 0 as well as the cost plan-total planned cost is 0 even though the resource rate is mentioned&amp;nbsp;&lt;/SPAN&gt;&lt;BR /&gt;&lt;SPAN&gt;Do we have to raise a case for this as this is unexpected behaviour&lt;/SPAN&gt;&lt;/P&gt;</description>
      <pubDate>Mon, 23 Jun 2025 10:11:30 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3296543#M47562</guid>
      <dc:creator>tejender</dc:creator>
      <dc:date>2025-06-23T10:11:30Z</dc:date>
    </item>
    <item>
      <title>Re: total planned cost on resource_plan and cost_plan is different and i want to make it similar</title>
      <link>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3312827#M47703</link>
      <description>&lt;P&gt;Yes please do&lt;/P&gt;</description>
      <pubDate>Mon, 07 Jul 2025 14:40:56 GMT</pubDate>
      <guid>https://www.servicenow.com/community/spm-forum/total-planned-cost-on-resource-plan-and-cost-plan-is-different/m-p/3312827#M47703</guid>
      <dc:creator>Arnab19</dc:creator>
      <dc:date>2025-07-07T14:40:56Z</dc:date>