Seems like a simple question but cant find answers for it.
How can we put a project on hold using SN PPS? Project state does not have on-hold status. Appreciate everyone's help.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-26-2017 07:01 PM
hello Wai,
i dont think "On hold" status is available out of the box.
Below link tells about customizing a state for project and project task(it might be helpful)
Customize a state for project or project task
Thanks
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎11-10-2021 02:31 PM
Hi, is there any new information on this? We also have a need to put projects on hold.
Thanks!

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎11-11-2021 05:00 AM
Hi Wais,
What we have done to achieve this is by adding a custom drop-down field named sub-state and adding a value as On-hold. We did not want to customise the OOTB state fields.
For cancelling a project we are using the OOTB state - Project Incomplete
Also, we have created a report for quality purposes which checks completed projects in an on-hold state.
Hope this helps.