# Rate Models

# Rate
Models {#ariaid-title1}

* Release version: Yokohama
* 
* Updated January 30, 2025
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 2 minutes to read

Summarize  
![AI sparkle icon](https://servicenow.com/docs/portal-asset/ai-sparkle-icon) Summarized using AI  
This content was generated using new OpenAI-powered functionality. Results are provided on an as is basis and are not guaranteed to be accurate or complete.  

## Summary of Rate Models

Rate models in ServiceNow enable you to derive date-effective, criteria-driven hourly rates for calculating planned and actual resource costs on projects or demands.
Unlike labor rates that rely solely on user attributes, rate models can use up to ten attributes from entities like projects, demands, users, and roles for more granular rate determination.
This flexibility helps you accurately assign costs based on various resource and project criteria.
Show full answer Show less  

## Key Features

* **Rate Lines:** A rate model consists of multiple rate lines, each defining an hourly rate for a resource, group, or role over a specific date range with unique criteria. Multiple rate lines can exist for the same criteria with different date ranges, provided they do not overlap.
* **Rate Model Processing:** By associating a rate model with a project or demand, ServiceNow evaluates rate lines to return the appropriate hourly rate during resource planning, allocation, and time card processing. If no rate model is linked, default labor rate cards are used.
* **Criteria Evaluation:** The system filters rate lines by requested date range and sequentially matches criteria columns, using exact values, NULL, or wildcard () matches. If multiple matches exist with different date ranges, rates are applied proportionally by date segments.
* **Rate Line Management:** You can create or modify rate models and rate lines within them to define rates based on criteria and date ranges. Rate lines can be exported to Excel or CSV files for bulk updates and re-imported to streamline management.

## Practical Use for ServiceNow Customers

By configuring rate models, you gain precise control over resource cost calculation in projects and demands, improving financial accuracy and planning. The ability to define multiple criteria and date-effective rates ensures flexibility for complex organizational needs. Export/import features facilitate efficient rate line maintenance, especially for large data sets.

When implementing rate models, link them to your projects or demands to enable automatic, criteria-driven cost derivation during resource allocation and time tracking, ensuring your cost data reflects current and relevant rate structures without manual adjustments.  
Use a rate model to derive date-effective, criteria-driven hourly rates for calculating
planned and actual resource costs for a project or demand.

Unlike
labor
rates,
which are based on the user attribute only,
a
rate model can derive
hourly rates
based on up to
ten
attributes. These attributes can be selected from
predefined
entities such as projects, demands, users, and roles.

## Rate lines {#rate-model__section_gyw_dnf_gfb}

A rate model is a collection of multiple rate lines. A rate line is a unique combination of
different criteria values that defines the hourly rate for a resource, group, or role for a
specific date range. For the same set of criteria, you can create multiple rate lines with
different rates for different date
ranges provided
that
the dates don't overlap.

## Rate model processing {#rate-model__section_lc4_vmf_gfb}

To derive hourly rates from a rate model for the resource plans and time cards of a project or demand, associate the rate model with the project or demand.  
Note:  
A project or demand without a rate model uses the labor rate cards associated with rate type to find a rate for the time cards.

The rate model associated with a project or demand evaluates the rate lines to find and return
the hourly rate that matches the requested criteria. The rates are derived from the rate model
during resource planning or allocation, and during time card processing.

The rate is returned in the functional currency specified in the matching rate line.
Figure 1. Rate model processing flow diagram

The following video describes how to set up a rate model and the evaluation method to find and
return the hourly rate
for
a request.

When a rate is requested, the rate model uses the following process.

1. Finds the rate lines in the requested date range and discards the remaining rate lines.
2. Evaluates the identified rate lines to find values matching the requested value in the first criteria column and discards the remaining rate lines. If the requested value is empty, it checks for rate lines containing
   NULL.

   If no exact match is found, it checks for the rate line having the value
   `All other (*)`.

   The evaluation is repeated for the other criteria
   columns in order of priority until all criteria columns are processed.
3. Returns the rate if one or more rate lines match the request.
   * If a single rate line is found, the corresponding rate is returned.

   * If multiple rate lines are found, the system determines the number of hours in the request that applies to each rate.
   * For example, say the rate requested is for resource allocation from July 1 to July 30. The rate model has one rate from July 1 to July 15 and a different rate from July 16 to July 30 for the same set of criteria. The rate model applies the first rate to the requested hours for July 1--15 and the second rate to the requested hours for July 16--30.

   {#rate-model__ul_ibj_dym_g3b}

   If no rate lines match the request, then the request uses the [default rate card](https://www.servicenow.com/docs/cbHm5iHaXzjpqnDPU2Re5w "Several components are installed with the Cost Management application.").
{#rate-model__ol_w3v_qz1_kfb}
* **[Create or modify a rate model](https://www.servicenow.com/docs/QEKLy77J7DxCFlG6Hd6v7g)**   
  Create or modify a rate model that can be linked to a project or demand to determine planned costs and actuals for their resource. The rate model provides date-effective, criteria-driven hourly rates for these investments.
* **[Define criteria of a rate model](https://www.servicenow.com/docs/Uhwbz8seBOcvgB4exWZvHw)**   
  Set the criteria of a rate model by adding attributes from a set of predefined entities to derive resource hourly rates based on the criteria.
* **[Create a rate line](https://www.servicenow.com/docs/x7MuNLSoNg0TwMYT4m4Hrw)**   
  In a rate model, create a rate line to define an hourly rate based on a set of criteria for a given date range.
* **[Export rate lines to a file](https://www.servicenow.com/docs/7noXaDSrKgb1VZh0W~MeKg)**   
  Export rate lines to a Microsoft Excel or CSV file to quickly update or add new rate lines and import them back into the rate model.
* **[Import rate lines into a rate model](https://www.servicenow.com/docs/f13ZlKnKNgPytKhVd4XUUQ)**   
  Use the import rate lines function to quickly add multiple rate lines from an export file into a rate model.