# Cost sources

# Cost sources {#ariaid-title1}

Release version: Australia  
Updated October 19, 2026  
![](https://www.servicenow.com/docs/portal-asset/ico-clock) 4 minutes to read
Summarize  
![AI sparkle icon](https://servicenow.com/docs/portal-asset/ai-sparkle-icon) Summarized using AI  
This content was generated using new OpenAI-powered functionality. Results are provided on an as is basis and are not guaranteed to be accurate or complete.  

## Summary of Cost sources

The Cost sources topic explains the various methods ServiceNow uses to generate expense lines for Configuration Items (CIs), tasks, and custom costs within the system.
It highlights three primary cost sources: CI costs, task costs, and custom generated costs (which require use of the ExpenseLine API).
Show full answer Show less  

## CI Rate Cards

CI Rate Cards serve as templates that define recurring costs for specific CI types, such as server models. They enable consistent cost assignment across similar CIs. Key functionalities include:

* Managing which CIs are linked to a rate card either manually or via the Update CI List feature, supporting bulk updates through Replace or Merge actions.
* Defining conditions (e.g., Table=Unix Server) to automatically associate relevant CIs.
* Specifying recurring costs (e.g., monthly server backup services) that generate expense lines for each linked CI.

## Distribution Costs

Distribution Costs represent broader bulk expenses that apply across multiple CIs where individual CI rate cards are not practical. For example, datacenter power costs amortized monthly can be evenly distributed to all servers using Distribution Rules. These rules define conditions (such as all installed servers) to allocate costs fairly for accurate cost reporting per server and cost center.

## Task Costs and Task Rate Cards

Task costs track expenses related to work activities, primarily using Task Rate Cards. These cards define cost calculation logic triggered when tasks close. Two main models are demonstrated:

* **Flat rate model:** For example, an Incident P1 rate card generates a fixed $150 expense when a priority 1 incident closes.
* **Time worked model:** For example, an emergency change request rate card calculates costs based on task time entries, applying user-specific or default hourly rates (e.g., $250/hr), and creates expense lines for each time worked record.

## Labor Rate Cards

Labor Rate Cards define hourly rates for groups of users based on attributes such as department, allowing standardized labor cost calculations without managing individual user rates. For instance, a Development rate card assigns a $100 hourly rate for users in that department when recording time worked.  
There are a several ways to generate expense lines for objects in the
system.  
These are generally classified as one of three types:

* CI costs
* Task costs
* Custom generated costs - these aren't covered in the demo data, refer to the ExpenseLine API for more information.
{#c_CostSources__ul_p5n_frt_jp}

## CI Rate Cards

A CI rate card is a template that defines costs for a particular type of CI. This example uses only server-related costs. Usually there are only a few different server models and the costs are the same for each model. CI rate
cards can define a template of costs for each model.  
The related lists contain information on how this rate card is used. The Configuration Items related list display the each of the servers that will use this rate card. This list of items can be managed manually with the Edit button or with the Update CI List related link. The rate card condition for this rate card is Table=Unix Server. Clicking the Update CI List related link shows two things:

* CIs that are a member of the rate card but don't match the condition.
* CIs that match the condition but aren't a member of the rate card.
{#c_CostSources__ul_fz5_srt_jp}

To "true-up" the rate card, use the Replace or Merge
button.  
In this case, there are two extra UNIX servers that aren't in the rate card. Use the Merge button to add them. The rate card now shows nine items.  
Note:  
Counts may vary if there are additional CIs in the instance.

The Rate Card Costs related list displays the recurring costs that all
of the servers will incur, in this case on a monthly basis.

Adding the Expense Line related list to the CI Rate Card form shows the list of expense lines that have been generated from this rate card's costs. Here are the expenses for the Server backup services for
two of the
servers.

## Distribution Costs

For more generic bulk costs that are generated by multiple CIs, distribution costs can represent the broader costs where individual CI rate cards don't apply. Navigate to AllFinancial ManagementDistribution Costs to view a few examples.

Select Datacenter Facilities (amort) from the
list.

In this example, the datacenter's power costs for a month have been amortized and represented
as a monthly recurring distribution cost.

This bulk cost should be distributed to all servers evenly to enable reporting on costs per server and cost center. This is accomplished with the Distribution Rule listed on the cost's form. To view the
distribution cost, select the reference icon for the All Installed Servers rule in the Distribution rule
field.

This rule takes the $5,500 and distributes it to each of the servers that match the rule
condition. The condition here is All servers with install status of installed. The '"View
Condition Results related link displays the current records matching the condition.

## Task Costs

Task-related activity can also generate expense lines to track the costs associated with
processing tasks. The primary method of generating task-related costs is to use Task Rate Cards.

## Task Rate Cards

A task rate card is a condition-based record that the system uses to determine how to
calculate the costs of a task.

To view an example, navigate to AllFinancial ManagementTask Rate Card and select Incident P1.  
Rate cards are processed whenever a task is closed. This processing is triggered by a business rule. The rate card contains the following information:

* When an incident with priority 1 - Critical is closed, it generates an expense line for $150.
* This is a flat rate defined for each P1 incident.
{#c_CostSources__ul_db4_d5t_jp}

The Expense Line related list displays the list of expenses that have
been created by this rate card.

Return to the Task Rate Card list and open the Change Request (emergency) rate
card.  
This rate card for emergency change requests demonstrates an example of creating a task cost based on the amount of time it took to work the task, instead of the flat rate model in the incident rate card.

* The Use time worked flag in the rate card tells the system to use the task time worked records associated with the task when determining the task cost.
* Processing this rate will:
  * Query the list of task time worked records for the task.
  * Attempt to resolve an hourly rate for the user in the task time worked record, or use the default rate of $250/hr defined in the rate card.
  * Generate an expense line for each time worked entry.
  {#c_CostSources__ul_byh_x5t_jp}
{#c_CostSources__ul_nyw_r5t_jp}

The Expense Lines related list shows the expenses generated from this
rate card.

## Labor Rate Cards

Labor rate cards are a way to define common patterns for hourly worker rates so rates need not be managed for each individual in the system.

To view the sample rates, navigate to AllFinancial ManagementLabor Rate Cards and select the Development rate
card.

The conditions state that for users in the Development department, time
worked costs will use $100 as the hourly rate.