# Legacy- Review external dependencies between projects

# Legacy- Review external dependencies between projects {#ariaid-title1}

* Freigeben Version: Australia
* 
* Aktualisiert 12. März 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 Minute Lesedauer

Review the external dependencies between projects in a portfolio to track projects
that are dependant on each other more closely.

## Vorbereitungen

Role required: it_portfolio_manager

Open demands and projects in the timeline view
of the portfolio planning workbench.

## Warum und wann dieser Vorgang ausgeführt wird

As a portfolio manager, you may want to know the projects which are dependent on each other so that these projects can be tracked more closely.

For example, project B
is dependent on project A (external soft dependency) and you want to make sure that
project A is executed on time so that the schedule of project B is not affected. The
Dependencies column shows that there is an outgoing
external dependency from project A and an incoming external dependency to project B.
You can the use the incoming dependency to determine whether a delay in project A
will affect project B.

## Prozedur

1. Click the show or hide columns in gantt icon (![show or hide columns in gantt icon]()) in the timeline view and add the Dependencies column if it is not visible.  
   The number of incoming and outgoing external dependencies are displayed, if any.
2. Click the external dependency in Dependencies column for the project.
3. In the Dependencies pop-up dialog, click a tab to review the dependency:  

   Inbound tab
   :   Tasks that have an incoming dependency from a project are
       listed.

   Outbound tab
   :   Tasks with an outgoing dependency to the project are listed.
   Abbildung : 1. External dependencies between projects
4. Click the project number in a tab to open and review the linked project in the planning console view.
{#review-external-dependencies-between-projects__steps_sfl_xt4_y1b}