Create a project task in the project workbench
Create a project task for a waterfall phase.
Avant de commencer
Role required: it_project_manager
Pourquoi et quand exécuter cette tâche
- For a manual project, the default constraint is Start On and cannot be changed.
- For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required.
- When the constraint is Start ASAP, the Planned start date is disabled.
- When you create an agile phase and associate a sprint, the start date of the task is set from the sprint start date and the constraint becomes Start On automatically.
Procédure
- Select a waterfall phase in the project workbench timeline.
- Select New in the detail view.
- Fill out the Project Task form.
- Select Submit.