    Procédure

    1. Navigate to Workspaces > Project Workspace.
    2. Depending on the projects that you want to view, select My Projects or All Projects.

      Projects on the homepage can be viewed in card or list view.

    3. Select a project to open it in the planning page.
      project-planning-page

      You can access and manage Planning, Details, Financials, RIDAC, Analytics, Docs, Status Reports, and Resources using the menu that appears when you select the Projects icon. This menu is also called as Level two (L2) menu.