Roll up expenses and resources in an engagement
Summarize
Summary of Roll up expenses and resources in an engagement
The new Advanced Audit plugin in the Audit Management application enhances how audit managers can consolidate and view costs, budgets, and resources associated with audit projects. This feature allows for an automated roll-up of expenses and resources from individual engagements to the parent engagement plan, providing a comprehensive overview of project finances.
Show less
Key Features
- Engagement Project Creation: When the Advanced Audit plugin is activated alongside the Project Portfolio Management application, engagement projects are automatically created for each audit plan.
- Budget Rollup: Users with the itportfoliomanager role can create project budgets that automatically reflect in the engagement's budgeted expenses, allowing for seamless financial management.
- Actual Expenses and Resources Rollup: Updates in actual effort from engagement projects are automatically reflected in the actual resources and expenses on the engagement.
- Resource and Cost Plan Integration: Resource plans and cost plans can be added to engagements, with values rolling up automatically, preventing manual entry in certain fields.
Key Outcomes
By utilizing the Advanced Audit plugin, audit managers can expect to achieve a consolidated view of audit project costs and resources, streamline budget management, and ensure accurate tracking of actual expenses and resource utilization. This functionality ultimately aids in better financial oversight and enhances the efficiency of audit project management.
Any audit project has associated costs, budgets, and resources. Roll ups of these costs, budgets, and resources enable the audit manager to view the entire costs and resources in a consolidated manner.
Starting with the new release, a new plugin called Advanced Audit has been introduced in the Audit Management application. When you activate the Advanced Audit plugin and install the Project Portfolio Management application, you can utilize the project management capabilities to automatically create engagement projects.
When an audit plan is created, the audit manager must be able to view the complete expenses and the resources involved in the engagement. Activating the Advanced Audit plugin enables the rollup of the expenses and resources cost of all engagements for a consolidated view. You can also use the advanced planning capabilities to automatically roll up the expenses and resources of each individual engagement to the parent plan of the engagements.
Project budget rollup
After an engagement project is automatically created, if the user has the it_portfolio_manager role, the user can create a project budget. When a budget is created, the budget cost gets copied over to the Budgeted expenses field of the engagement from the engagement project. When you use the advanced planning capabilities to automatically create a plan, the values in the expenses and the resources field are rolled up from the associated engagements and the engagement projects. To allocate a project budget, see Allocate budget to a project. If you allocate a project budget, then the data from the budget cost field gets copied over to the engagement. For example, if you have an engagement where the budget expense is $100. Then, if you create a project budget for the engagement project of this engagement, and enter the budget cost as $200, then the budget expense of $100 in the engagement is overwritten and replaced by $200.
Actual expenses and resources rollup
If actual effort is updated on an engagement project, then that value gets copied over to actual resources on the engagement. The Actual resources and Actual expenses both are copied over from the Actual effortand Actual cost fields.
Resource plan rollup
With Project Portfolio Management, you can add resource plans and cost plans to an engagement. To learn how to create an engagement with advanced planning, see Create an engagement with advanced planning
After you create a resource plan and it is in the Allocated state, all the confirmed and allocated hours from the resource plan are summed up in the planned resources on the engagement project. When a resource plan is created, you cannot manually enter the hours in the Planned resources field on the engagement form as the values get automatically rolled up. To manually enter hours in the Planned resources field, you must delete the resource plan that you have created.
Cost plan rollup
If you create an independent cost plan that is not created as a result of a resource plan, then you cannot manually enter values in the Planned expenses field on the engagement form. You can still edit the Planned resources field.