Close a risk event

  • Release version: Australia
  • Updated March 12, 2026
  • 1 minute to read
  • Close a risk event to complete the risk events life cycle. A user with the sn_risk.manager role must close the risk event after verifying that all associated open issues and remedial tasks are closed.

    Before you begin

    Role required: sn_risk.manager

    Procedure

    1. Navigate to All > Risk Events > Assigned to Me.
    2. Open the record that you want to close and verify if all the associated tasks and issues are closed.
    3. Click Close.