Create a sprint in CWM

  • Release version: Australia
  • Updated March 12, 2026
  • 1 minute to read
  • Create a sprint with custom duration and capacity to enable your team to plan and execute their work in an Agile methodology in Collaborative Work Management.

    Before you begin

    Role required: sn_cwm.cwm_user

    Procedure

    1. Navigate to Workspaces > Collaborative Work Management.
    2. From a Space, select a Board that you're performing sprint planning for.
    3. Select the Sprint planning tab.
    4. If there are no sprints in your CWM Board, you can use the Plan a Sprint form in the Sprints section.
    5. If there are existing sprints, choose an option to create a new sprint.
      ChoiceSteps
      Create a sprint with the same duration and story points capacity as the existing sprint Select Add another Sprint.
      Create a sprint with different duration or story point capacity
      1. Select Create Sprint.
      2. Fill in the details.
      3. Select Create Sprint

    What to do next

    Plan work items into sprints in CWM.