# Configure parameters displayed on project cards

# Configure parameters on project cards in Project Workspace {#ariaid-title1}

* Release version: Australia
* 
* Updated March 12, 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 3 minutes to read

Configure the parameters that are displayed on a project card in My Projects Space page of classic Project Workspace. A card shows the project
summary so that project managers can quickly gauge project status and health by looking at
the card.
Important:  
Classic Project Workspace is being prepared for future deprecation. It will be hidden and no longer available for installation but will continue to be supported. For details, see the [Deprecation Process \[KB0867184\]](https://hi.service-now.com/kb_view.do?sysparm_article=KB0867184) article in the Now Support knowledge base. Use new Project Workspace with enhanced UI to help you efficiently manage your projects.

## Before you begin

Role required: it_pps_admin

## About this task

The project workspace overview page My Projects Space displays
the projects as cards based on the filter criteria. The cards have a color band at
the top. The color of the band is based on the Status field
in the respective project record. Each card further displays the following
information about the project in three rows:

* Row 1 displays project name, state, project manager name, and important project dates. The displayed project dates are based on the current state of the project:
  * If the project state is Pending or Open, planned start date and planned end date are displayed.
  * If the project state is Work in Progress, actual start date and planned end date are displayed.
  * If the project state is Closed, actual start date and actual end date are displayed.
  {#configure-project-card-parameters__ul_edx_vtq_3bb}
* Row 2 displays Status, Percent complete, and Phase columns from project \[pm_project\] table. The number of displayed columns in this row is fixed to 3, but the columns to be displayed can be configured in \[pm_home_page_config\] table.
* Row 3 displays the following project information based on the current state of the project.
  * Open risks, open issues, actions, and overdue tasks of the project under Updates heading.
  * Date and short description of the last missed milestone task under Last missed milestone heading.
  {#configure-project-card-parameters__ul_nrw_y5q_3bb}The parameters displayed are derived from the records in \[pm_home_page_card\] table. In \[pm_home_page_card\] table, each project state is assigned some parameters to be displayed.

{#configure-project-card-parameters__ul_l5z_fz4_dbb}

You can configure the information which is displayed in row 2 and row3 on a card.

## Procedure

1. Navigate to AllProject AdministrationProject Workspace.
2. Select a table for which you want to change the card configuration, for example, select `Project[pm_project]`.
3. Set the display columns for row 2 of the card in PM Home Page Configuration \[pm_home_page_config\] table.
   1. Select the columns to be displayed in Column-1, Column-2, and Column-3 fields.
   2. Click Update.

   {#configure-project-card-parameters__substeps_eyv_33l_2bb}  
   The selected columns appear in row 2 of the project cards.
4. Set the parameters for row 3 of the card in PM Home Page Card \[pm_home_page_card\] table.  
   In \[pm_home_page_card\] table, each project state is assigned the parameters that are required to be displayed on a project card in third row.
   1. Click New in PM Home Page Card related list.
   2. On the form, fill in the fields.  
      {#configure-project-card-parameters__table_project_card_config__entry__2}

      | Field | Description |
      |-|-|
      | Order | Position at which the parameter appears in row 3 of the card. |
      | State | Project state for which the parameter needs to be added. |
      | Value | Section to be displayed for the selected state in row 3 such as Updates and Last missed milestone. |
      | Content | JSON field to add the parameters to be displayed under the selected section for the selected state. |
      [Table 1. PM Home Page Card form]

      {#configure-project-card-parameters__table_project_card_config}

      The following screenshot shows a JSON example of adding Risks, Issues, Actions, and Overdue tasks parameters under Updates heading for Open state.
   3. Click Submit.  
      Note:  
      Use the same steps to change a display parameter assigned to a state.

   {#configure-project-card-parameters__substeps_zhl_m4l_2bb}  
   The parameter is added or updated for the selected state. It appears under selected section in row 3 on the project cards for the state it was added.

*[\>]: and then