Realign resource assignments with project dates
Realign or synchronize the resource assignment dates with the project task dates. This synchronization helps to schedule and align the resource assignments with the timeline of project task.
Before you begin
Role required: it_project_manager
About this task
When you change project dates, a prompt appears to realign resource assignments to the updated dates. However, if you skip this step, resource assignments go out of sync with the project. To prevent this, use the sn_pw.resource_assignment_auto_sync_enabled system property to realign all resource assignments across projects automatically on a periodic basis.
Procedure
Result
The resource assignments dates are synchronized with the project task dates.
Realign resource assignments with project dates
Jason (Project Manager) updates the end date of a project from June 30 to August 31. The system prompts the Jason to realign resource assignments, but Jason closes the prompt without running the realignment. As a result, resource assignments still reflect the original end date of June 30. If the system property is configured, it runs automatically and realigns all resource assignments to the updated project dates without any manual action required.