# Update the task dependency

# Update task dependency details in Project Workspace {#ariaid-title1}

* Release version: Australia
* 
* Updated March 12, 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

Update the details of the dependency including its type and lag time from Project Workspace.

## Before you begin

Role required: it_project_manager

## Procedure

1. Open a project from the home page of Project Workspace.  
   For information, see [Access the Project Workspace](https://www.servicenow.com/docs/NizzG8MYmtX6E2dj4LyjPw "Learn how to navigate to the new Project Workspace and open a project in the planning page.").
2. Open the dependency side panel in one of the two ways.

   | Option | Action |
   | From the data grid | From the dependency column, select the dependency of the task. |
   | From the timeline view | Select the dependency line. |
   |-|-|

   {#update-the-dependency-details-for-tasks-from-project-workspace__choicetable_vbz_g1z_hsb}
3. Edit the fields.
4. Select Update.