Manage demand budgets

  • Release version: Australia
  • Updated July 25, 2026
  • 1 minute to read
  • Allocate, manage, and approve budget for your demands. Lean budgeting allocates budget for short planning cycles across fiscal periods, such as monthly, quarterly, or yearly. This approach differs from allocating budget to the complete duration of a demand.

    Before you begin

    Procedure

    1. Navigate to Workspaces > Strategic Planning Workspace.
    2. Select the Demands icon .
    3. Open a demand from the List page.
    4. Select Financials from the navigation menu.
    5. Select Budget allocation from the Display mode list.
    6. Manage the budget for the selected time scale at the monthly, quarterly, or yearly level using one of the following methods.
      • Double-click each cell in the Budget column and enter the value.
      • Select Copy cost as budget from the Budget column options to copy Forecast value as budget.
      • Edit the budget values using the in-grid editing feature after copying Forecast to budget.
      • Unapproved budget values are marked with the icon.
      Note:
      Negative budget amounts are supported. If you enter a negative Capex Budget or Opex Budget amount, or the associated cost plan has a negative total planned cost, the demand budget is still distributed across the cost plan breakdowns and rolled up to the demand financials.
    7. Select Approve budget.
      The Approve budget confirmation dialog opens. The Create a financial baseline for this budget approval option is selected by default. This option captures the latest budget and financial estimates.
      Tip:
      The financial baseline created while approving the budget can be compared with the future baselines once the actual expenses are captured to track financial performance.
    8. In the confirmation dialog, select Approve.