Create a test plan
Create a test plan to detail how a product or a feature is to be tested.
Before you begin
Role required: tm_test_manager or tm_tester
Procedure
What to do next
You can use the related links and related lists of the new test suite for the
following actions:
- Add existing test cases to this test plan from a test suite by clicking the Add Test Cases from Test Suite related link.
- Add new test cases to this test plan from the Test Cases related list. For more information, see Add a new test case to a test plan.
- Save this test plan as a new test suite by clicking the Save as Test Suite related link. A new test suite is created with all the test cases of this plan making them available to add to another test plan.
- Start the test plan and notify the testers about the target end date for testing by using the Notify Tester related link. For more information, see Initiate guided test execution.
- Cancel the test execution by clicking Cancel test execution related link. This link is available only if you've used the Notify Tester related link and started the test plan. For more information, see Cancel guided test execution.
- View all the test cases in a Visual Task Board (VTB) by clicking Show Visual task Board related link. The VTB shows test cases in lanes organized by their execution states.
- Create a copy of this test plan by clicking Copy Test Plan.
- View the test execution summary and sign off the test plan by clicking the Sign-off Test Plan related link.
- View the Test Plan Defects related list for the list of all the defects logged from the test cases.
Display test plan execution start and end dates
Add the planned and actual start and end date fields on the Test Plan form to see the execution date information.
Before you begin
Role required: tm_test_manager or tm_tester
About this task
Configure the Test Plan form layout to display the planned and actual start and end dates for the test plan.
Procedure
Result
The Test Plan form is displayed with the newly added date fields.