Use the project task creator to create multiple tasks at once.
始める前に
Role required: it_project_manager
手順
-
In the Project form, right-click the header bar and select Project
task creator.
-
Enter the number of tasks to create.
-
Select the Create FS dependency check box to create a
finish-to-start dependency between these tasks (when the first task finishes,
the next task starts).
Clear the check box to create the tasks with no dependencies.
-
Select OK.
The new tasks appear in the Project Tasks related list. The application automatically creates a task Number and a Short Description that starts
with Auto Created Task, followed by a number when more than one task is created.