You can configure the planned task fields to roll up the field values in the parent
entity.
始める前に
Role required: admin
このタスクについて
By default the following fields are configured to roll up for
any planned task and planned task derivatives:
Cost, Budget, Effort, Actual date, Planned date, Duration, Percent Complete
手順
-
Navigate to .
-
Open the Planned task rollup table.
-
In the Related links, click Show List.
-
Click New.
-
Fill out the Planned task rollup form (see table).
-
Click Submit.
表 : 1. Planned task rollup form fields
| Field |
Description |
| Child |
Select the table you want to include or
exclude. |
| Field |
Select the column name you want to include or
exclude. |
| Navigator |
The reference column of the parent to which the value
must be rolled up. |
| Parent |
Select the parent table. |
| Application |
Auto-generated value. |
| Rollup |
Select the check box to allow roll up. Leave the
field unchecked to exclude the field from
rollup. |