Resource event modifications

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Resource events that aren’t part of a resource plan can be modified.

    You can only modify events you created for yourself in the "My Calendar" module. If a resource manager added an event to your calendar, then only the resource manager can modify the event.

    Resource managers can modify an event that is part of a resource plan by deleting the event and creating a one. For example, a resource manager allocates a resource to a task on a resource plan and then wants to change the task work type to Phone Call. The resource manager must delete the event and then create another event with the work type set to Phone Call.