Execution plan tasks
An execution plan contains one or more execution plan tasks, such as for obtaining approval. Execution plan tasks are assigned to a fulfillment group.
Each task represents work to be completed by a specific group as part of the overall request fulfillment process.
Administrators create templates for tasks as part of defining an execution plan. The catalog tasks themselves are then created when the relevant item is requested, based on these task templates.
Set up an execution plan approval task
Approval tasks are specific types of tasks within execution plans.
시작하기 전에
Role required: admin
이 태스크 정보
If an approval task is rejected, the execution plan can roll back to a previous task, but the approval record does not roll back.
To set up an approval task including a rollback action:
프로시저
Set up a fulfillment group
Fulfillment groups perform the tasks related to fulfilling an order.
시작하기 전에
Role required: admin
이 태스크 정보
To create a group specifically for order fulfillment:
프로시저
Delivery information for tasks
When managing execution plans, catalog administrators can specify the delivery information to provide an estimated date of delivery based on the execution plan.
Use the Total delivery time field to specify an estimated delivery time for each task in your execution plan. This estimate is calculated based on the combined total of times for the tasks in that execution plan.
By default, time estimates do not use a "working days" calendar system, but are based on simple elapsed time. For example, for a 5-day execution plan, if you submit the request on a Friday, the delivery date is Wednesday of the following week. This estimate means five elapsed days later, even if your organization does not work on weekends.
Setting the calendar to Monday through Friday (9-5) defines each day as being eight hours long, but the task delivery time day is 24 hours. If you create a task that takes one day (24 hours), the plan calculates the task as needing three work days (which are eight hours each) for the total delivery time. Similarly, if a task takes two days (48 hours), the plan calculates eight days of total delivery time. This total breaks down as six work days of eight hours each and, because six days are longer than the five-day work week, two weekend days. When assigning delivery times, keep this calculation process in mind.
Use the On Calendar field to specify a calendar system to apply to the execution plan, to help estimate more accurate delivery times.
Skipped tasks
If a task is skipped, the request fulfillment process moves on to the next task.
If the last task in an execution plan is skipped, the process is finished and the appropriate request item is closed as complete. Skipped tasks have their state set to Closed Skipped and display as gray boxes on a requested items list.