Configure an application quota rule

  • Release version: Australia
  • Updated March 12, 2026
  • 1 minute to read
  • Configure an application quota rule to limit the number of events or jobs that can run in an application's scope within a specified time.

    Before you begin

    Role required: admin

    About this task

    You must be in the application scope of the application for which you want to create a rule.

    Procedure

    1. Navigate to All > System Definition > Application Quota Rules.
    2. Select New.
    3. On the Application Quota Rule form, fill in the fields.
      For a description of the field values, see Application quota rule form.
    4. Set a condition to specify when the application quota rule should take effect.
      The application quota rule condition builder displays conditions that are only applicable to transactions. For a description of the condition builder options, see Application quota condition builder.
    5. Select Submit.