# Modify a project task dependency

# Modify a project task dependency {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

You can modify a dependency when editing the tasks that are linked in the dependency,
the dependency type, or the lag time.

## Before you begin

Role required: it_project_manager

## About this task

Project task dependencies are saved on the Planned Task Relationship
\[planned_task_rel_planned_task\] table. You can access dependencies from the planning
console.

## Procedure

1. Double-click a dependency on the Gantt chart of the [planning console](https://www.servicenow.com/docs/owIml6EpzZG1qKyFhs9XqA "The planning console is a centralized interface for the Project Management application.").
2. Modify any of the fields (see table).  
   Figure 1. Planned Task Relationship form  
   {#t_ModifyProjectTaskDependencies__table_ltr_5hy_ds__entry__2}

   | Field | Description |
   |-|-|
   | Predecessor | The predecessor, or determiner, in the relationship. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks. |
   | Successor | The successor in the relationship. The successor depends on the predecessor. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks. |
   | Type | The type of relationship, which is always Predecessor of::Successor of. Do not change this value. |
   | Sub Type | The type of dependency. See [Project task relationships and dependencies](https://www.servicenow.com/docs/19ZkzZ1W90OCBNOQbAt65g "The Project Management application enables you a create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks.") for a description of each type. |
   | Lag | The lag time between the tasks. The Enter the days, hours, minutes, and seconds for the lag. Lag time can be positive or negative. |
   [Table 1. Planned Task Relationship form fields]

   {#t_ModifyProjectTaskDependencies__table_ltr_5hy_ds}
3. Click Update.  
   You can view dependencies in the Project Task related list on a Project or Project Task form and from the Project Tasks list on the workbench. These columns show the dependencies:
   * The Dependency column shows the successor task in the relationship.
   * The Dependencies column shows the dependency value. See [Predecessor dependencies in the planning console](https://www.servicenow.com/docs/p2XtGZIvT2fgZGxVkWQjPw "In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values.") for a description of what you see in this column.
   {#t_ModifyProjectTaskDependencies__ul_vd1_zrb_ms}