  • Apply your change approval policy in the Change Management Flow Designer action to control the approval process for a change request. You can create user and group approvals according to a change approval policy record.

    Before you begin

    Role required: admin

    About this task

    This flow action uses the Ask For Approval flow action to apply approvals that are derived from the Change approval policy. When approvals are being generated, the Ask For Approval action avoids generating more than one approval for the same user. For example, if the policy requires approval from two groups and both groups have the same user, then the shared user is notified only once for the approval.

    Procedure

    1. Navigate to All > Process Automation > Flow Designer > Flows.
    2. Select the flow that you want to apply the change approval policy to.
    3. Select Action > Installed Spokes > ITSM > Change > Apply Change Approval Policy.
    4. On the form, fill in the fields:
      Table 1. Apply Change Approval Policy form
      Field Description
      Action Label Unique label for the action.
      Policy [Change Approval Policy] Policy that you want to apply to your Change request.
      Change Request Source of the change request required by the policy. Select this field using the data pill picker icon ( data pill picker icon.). Alternatively, you can select the change request from the Change Request list.
      Due Date Due date for the approval policy. Select one of the following options:
      • None: The approval has no due date.
      • Approve: Automatically approve the approval policy on the due date.
      • Reject: Automatically reject the approval policy on the due date.
      • Cancel: Automatically cancel the approval policy on the due date.
    5. Click Submit.