You can modify a dependency when editing the tasks that are linked in the dependency,
the dependency type, or the lag time.
Before you begin
Role required: it_project_manager
About this task
Project task dependencies are saved on the Planned Task Relationship
[planned_task_rel_planned_task] table. You can access dependencies from the planning
console.
Procedure
Double-click a dependency on the Gantt chart of the planning console.
Modify any of the fields (see table).
Figure 1. Planned Task Relationship form
Table 1. Planned Task Relationship form fields
Field
Description
Predecessor
The predecessor, or determiner, in the relationship.
You can select a new task. However, it is a good
practice to delete the relationship and create a new
relationship between the correct tasks.
Successor
The successor in the relationship. The successor
depends on the predecessor. You can select a new task.
However, it is a good practice to delete the
relationship and create a new relationship between the
correct tasks.
Type
The type of relationship, which is always
Predecessor of::Successor of.
Do not change this value.
The lag time between the tasks. The Enter the days,
hours, minutes, and seconds for the lag. Lag time can
be positive or negative.
Click Update.
You can view dependencies in the Project Task related list on a Project or
Project Task form and from the Project Tasks list on the workbench. These
columns show the dependencies:
The Dependency column shows the successor task
in the relationship.