# Resource plans

# Resource plans {#ariaid-title1}

* Release version: Xanadu
* 
* Updated August 1, 2024
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 5 minutes to read

Resource plans are the key element in resource management.  
Important:  
Resource plans in Resource Management will no longer be available for new customers from future releases.

You're encouraged to work on resource assignments which offers more flexibility [Create resource assignments and operation resource assignments in Resource Management Workspace](https://www.servicenow.com/docs/oMqrNt7Pcx91z7WkpfyrWQ "Create and assign resource assignments and operation resource assignments from Resource Management Workspace.") using Resource Management Workspace or Project Workspace.

Resource requesters, such as project managers, [create
resource plans](https://www.servicenow.com/docs/2Ox~dZVXDqXCMtiFEl75mw "You can create a resource plan from the Resource Management application for any task such as demand, project, project task, incident, problem, or change. You can edit and adjust the plan until you submit it for approval.") to ask for resources, track effort, and track costs. Resource managers
modify and approve resource plans before the plans are used.

All resource plans for a task appear on the Resource Plan related list
of the Project task form, where resource requesters can access them.  
Figure 1. Resource plan on the Project form  
Resource plans progress through several states.{#c_ResourcePlans__table_qy4_lx4_4s__entry__2}

| State | Description |
|-|-|
| Planning | Planning is the default state when a resource requester creates a resource plan. Any plan in this state can be edited. [Requested Allocations](https://www.servicenow.com/docs/quFq8n529lpyHCx1jp3pfA "Requested Allocations are automatically created when a resource plan is submitted and is in Planning state. If required, resource requesters can create new requested allocations for a resource plan in Planning or Rejected state. Resource managers can create requested allocations for the plans in Requested state.") are created when a resource plan is in Planning state. When a resource requester asks for a change to a plan that was already submitted, the plan reverts to the Planning state. |
| Requested | Resource requester submits a resource plan for resource managers review by selecting Submit. The resource plan then moves into the Requested state. Resource managers confirm and allocate resources or reject the plan, and finally close the plan. The resource requester can request a group, specific users in a group, or a specific user to work on the selected task. After you submit the plan for review, a resource manager can confirm, and then allocate some or all the requested users. If the task requires more than one user or groups, multiple resource plans can be created for the given task. |
| Rejected | Resource manager can reject a resource plan by selecting Reject. The resource plan then moves into the Rejected state. Rejected plans stay in that state until changes are made and the requester can re-request the resources. |
| Confirmed | After the plan is requested, the resource manager can block/confirm the resources for future projects and demands. The resource plan then moves into the Confirmed state. Only a resource manager can modify the plans in Confirmed state. Soft allocations are created when the resource plan moves to the Confirmed state. |
| Allocated | After the plan is confirmed, the resource manager can review the plans, view availability, change resource preferences and perform the resource allocation. The resource plan moves into the Allocated state. A resource manager can only cancel, complete, or modify it. Soft allocations are converted to hard allocations when the resource plan moves to the Allocated state. Note: You can also set a plan to the Allocated state directly from the Requested state using Confirm and Allocate option. |
| Completed | After all associated tasks and projects are complete or canceled, an Allocated resource plan can be completed. This deletes all the resource allocations for the resource plan post the completion date. |
| Canceled | A plan can be canceled if the allocations are no longer required. This removes all past and future allocations. A canceled resource plan can be brought back to the Planning state if it has no past allocations. Resource plans in Planning, Requested, Confirmed, or Allocated state can be canceled. |
[Table 1. Resource plan states]

{#c_ResourcePlans__table_qy4_lx4_4s}  
Figure 2. States in Resource Management  
Note:  
When a resource requester wants to change a plan that was already submitted for review (in Requested or Confirmed state but not yet allocated), the requester can [request a
change](https://www.servicenow.com/docs/HT0sswgDRChp0JdbcYc3sw "Request a change to the resource plan to modify a resource plan after you’ve submitted it for review."). The plan then moves back to the Planning state.

Resource Management supports time zones, which are important in the My Calendar and Resource
Workbench modules.

## Modifications in Confirmed or Allocated state

Only a resource manager can modify a resource plan in the Confirmed or Allocated state.  
The effects of modification in header area on a resource plan form in Confirmed state are:

* All soft [allocations](https://www.servicenow.com/docs/u3FY0aRJNPxbdq2IZxo9UA "After resource requesters create a resource plan, resource managers can confirm the resources to move the plan to the Confirmed state. Resource managers can then allocate resources to the plan and move it to the Allocated state.") are deleted.
* Requested allocations are re-created with changed values.
* Resource plan moves back to the Requested state.
{#c_ResourcePlans__ul_g3b_ms5_mx}  
The effects of modification in header area on a resource plan form in Allocated state are:

* All resource allocations (soft and hard) are deleted.
* Requested allocations are re-created with changed values.
* Resource plan moves back to the Requested state.
{#c_ResourcePlans__ul_sqc_qs5_mx}

The resource manager can also modify or delete the past dated resource allocations for
Allocated resource plans if no actual hours are recorded for those resource allocation records.
When a user submits a time card, upon approval of the time card, actual hours are updated for an
allocation record.  
Note:  
The resource plan does not move back to the Requested state if the changes are made to allocation records only.

## Request type

You can request a resource plan using one of the following options:

* Hourly: The request is in terms of the number of hours the resources are necessary.
* FTE: The request is in terms of an equivalent value that represents full-time work. When the request type is FTE, planned hours are calculated as: `Average Daily FTE * number
  of working days in resource plan * the FTE value`. The average daily FTE hours are specified in User and Group records. If there is no value specified at User or Group record, the average daily FTE hours is taken from the Default Average Daily FTE property.

  The number of working days is calculated based on the users schedule for a user
  resource or the default schedule for group resources. The default schedule is taken from the
  Default Schedule Name property.

  For example, say that the average daily FTE for a group
  is 40 hours, the resource plan period is from September 1 to September 10, and the FTE is
  0.5.

  Assuming 8 working days during the plan period, planned hours = `40 * 8 *
  0.5` =160 hours.  
  Note:  
  Capacity is not derived from FTE, but from schedules. Both FTE and schedules must be in synchronization with each other.
* Person days: The request is in terms of person days. When the request type is person days, planned hours are calculated as: `Total number of person days * Average Daily FTE
  Hours/Hours Per Person Day`.

  For example, say the Average Daily FTE Hours/Hours
  Per Person Day for a group is 8 hours, and the person days is 3. Then, planned hours =
  `8 * 3` = 24 hours.
{#c_ResourcePlans__ul_lcz_1ms_lt}

## Resource plan costs

Resource plan costs can be tracked directly in the [resource plan](https://www.servicenow.com/docs/6kM8z9C5mV8lt2A5Nvftug "Field descriptions for the resource plan form fields.") record. Resource plan costs are divided into planned, allocated, and actual.

If the Rate override option in a resource plan is selected, the hourly
rate for calculating the corresponding resource plan cost is derived from the rate specified in
the Resource rate field.

If a [rate
model](https://www.servicenow.com/docs/CXfScC54nNogRPJmwVcGuQ "Use a rate model to derive date-effective, criteria-driven hourly rates for calculating planned and actual resource costs for a project or demand.") is associated to the project or demand, the hourly rate is derived from the rate
model. Whenever the hourly rates in the associated rate model change, you must [recalculate the
resource costs](https://www.servicenow.com/docs/XrYfI6wKlZr5VrJPDgq2~g "Recalculate the resource costs of an individual resource plan for a project or demand whenever the hourly rates change in the associated rate model.") of the resource plan to reflect the new rates.

If rate model is not available, the hourly rate for calculating the corresponding resource
plan cost is derived from labor rate card.

Projects and Demands can have multiple resource plans. The aggregated costs for all resources
plans roll up to the Planned Cost and Allocated Cost fields and the Resource Cost section of both projects
and demands.
* **[Create a resource plan](https://www.servicenow.com/docs/2Ox~dZVXDqXCMtiFEl75mw)**   
  You can create a resource plan from the Resource Management application for any task such as demand, project, project task, incident, problem, or change. You can edit and adjust the plan until you submit it for approval.
* **[Use Resource Finder to analyze resource availability](https://www.servicenow.com/docs/qCVY8iDq2hmTQTAbDx5eWQ)**   
  Search and analyze resource availability using the Resource Finder, so that you can create resource plans for a project or demand.
* **[Create an operational resource plan](https://www.servicenow.com/docs/41T9Xw3NPCHHmQUK0MxWaw)**   
  Create an operational resource plan and allocate a certain portion of your team capacity for operational work, such as administration, meeting, or training.
* **[Request resources](https://www.servicenow.com/docs/fBL8RFMkuQ5s6qnneBQMXw)**   
  After you create a resource plan, request resources from the resource manager.
* **[Confirm a resource plan](https://www.servicenow.com/docs/MZJlTG6Ei2QBUluMiMSN~Q)**   
  As a resource manager, you can confirm or block the resources after a resource plan is requested. The resource plan must be in the Requested state to be confirmed.
* **[Confirm and allocate a resource plan](https://www.servicenow.com/docs/NijIoFrBiHHDZcwYk6frZA)**   
  After the resource plan is requested, as a resource manager, you can directly allocate the resources. To confirm and allocate, the resource plan must be in the Requested state.
* **[Request a change to a resource plan](https://www.servicenow.com/docs/HT0sswgDRChp0JdbcYc3sw)**   
  Request a change to the resource plan to modify a resource plan after you've submitted it for review.
* **[Recalculate costs of a resource plan of a project or demand](https://www.servicenow.com/docs/XrYfI6wKlZr5VrJPDgq2~g)**   
  Recalculate the resource costs of an individual resource plan for a project or demand whenever the hourly rates change in the associated rate model.
* **[Update cost plan related to a resource plan](https://www.servicenow.com/docs/7AKxQpRtaSi1U11pCJ23mA)**   
  If a resource plan is associated to a project, project task, or demand and has a related cost plan, then a requester or a resource manager can update the related cost plan after updating the resource plan.
* **[Complete a resource plan](https://www.servicenow.com/docs/4VDKa8LKHRw8t4vt1TJRzA)**   
  After all associated tasks and projects are complete or canceled, a resource manager can move the resource plan to the Complete state, which closes it.
* **[Cancel a resource plan](https://www.servicenow.com/docs/x287ZCd~SJsWryuDNTlDkw)**   
  If a resource plan is no longer needed, you can cancel it which also cancels its past and future allocations.
* **[Delete a resource plan](https://www.servicenow.com/docs/feva46OF2ymFM0GfgFH8Ng)**   
  Deleting a plan also deletes all associated resource allocations.
* **[Extend a resource plan](https://www.servicenow.com/docs/lQCFPut~Zek1KuTqF12Ruw)**   
  You can extend the date of an allocated resource plan and allocate resources for the extended period.
* **[Request extension of an allocated resource plan](https://www.servicenow.com/docs/4Rxx2aJq6y3LgAPYL_AOUg)**   
  As a project manager, you can request the extension of an allocated resource plan.
* **[Allocate resources for the extended period](https://www.servicenow.com/docs/485jUu_E3MokKk4O~UG5Rg)**   
  As a resource manager, you can allocate resources for the extended period.
* **[Reduce the duration of a resource plan](https://www.servicenow.com/docs/MxmgUpRTdXs4Vl8rqc5JEQ)**   
  Reduce the duration of an allocated or confirmed resource plan and deallocate resources in one action without having to do it individually for each resource.
* **[Time zones in resource plans](https://www.servicenow.com/docs/rsT~bHLtzxjA4EtGC69yVQ)**   
  Time zones are important in resource management when the users and groups doing the resource tasks are located in different locations.
* **[Associate a time card with a resource plan](https://www.servicenow.com/docs/JE4wxyQu_MiVQmF28HCQDg)**   
  If one resource is allocated to identically named tasks in two resource plans, use the following procedure to specify the resource plan the time card should be allocated to.