# Move a resource assignment in Project Workspace

# Move a resource assignment in Project Workspace {#ariaid-title1}

* Release version: Yokohama
* 
* Updated July 1, 2025
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

Move the resource assignment to a new start and end dates to accommodate changes in task scheduling or resource allocation. Shift assignments to balance workloads across resources and avoid over-allocation.

## Before you begin

Role required: resource_user, resource_manager

## About this task

* When you move an assignment to a new start and end dates, the initial requested or approved efforts are retained for the latest duration.
* When an assignment is moved, the Ready for review state is retained and the assignment remains accessible to resource managers for work allocation.
* You cannot move a resource assignment if actuals efforts are entered for the work.
* New assignment dates should be within the task duration dates.
{#move-resource-assignments-project-workspace__ul_rdy_rxb_wfc}

## Procedure

1. Navigate to WorkspacesProject Workspace and open a project.
2. View the resource assignment pane by enabling the Resource assignments toggle button.  
   Note:  
   If the sn_pw.enable_resource_planning property is set to true, then the Resource assignment toggle button and resource assignment pane are displayed in Project Workspace. The default value is false. You must have the pps_admin role to enable this property.
3. Select a project task to view the assignments associated to the task.
4. From the resource assignment pane, select the row context menu (![Row context menu.]()) and then select Move.
5. From Move assignment modal, select a New start date using the date picker modal.
6. **Optional:** Change the assignment status using the New status list to one of the following available statuses.  
   Changing the status is restricted to the resource_manager role.
7. Select Confirm.  
   When you move the resource assignment for a group, the assignments are moved for all members of that group. You cannot move assignments for individual users within the group or for child resource assignments.
**Related tasks**   

* [Extend a resource assignment](https://www.servicenow.com/docs/UkrDfeaAeCabWyCZh8xadQ "Extend the date of an allocated resource assignment and allocate resources for the extended period.")
* [Update resource assignment from Project Workspace](https://www.servicenow.com/docs/lz4pHE~qUyReMlngyj3yzw "Update a resource assignment that is associated with a project or project task.")
* [Delete a resource assignment from Project Workspace](https://www.servicenow.com/docs/dkn6f9XMXVS6mB3W9J3oaQ "Delete a resource assignment from Project Workspace. Deleting an assignment also deletes all associated resource allocations.")
* [Update the resource allocation in a heatmap](https://www.servicenow.com/docs/6eFmyya9Icu1HYxeo7hMBQ "Use the allocation heatmap capability in Project Workspace to view and update the resource allocation.")
* [Realign resource assignment to project task](https://www.servicenow.com/docs/XVIK9LVONItP9NNS7OJYYQ "Realign or synchronize the resource assignment dates with the project task dates. This synchronization helps to schedule and align the resource assignments with the timeline of project task.")

*[\>]: and then