---
sourceDocument: Zurich Strategic Portfolio Management
sourceDocumentLink: https://www.servicenow.com/docs/r/zurich/it-business-management

 Release :

    - zurich

ft:locale :

    - en-US

ft:publication_title :

    - Zurich Strategic Portfolio Management

ft:clusterId :

    - itbm

bundleId :

    - itbm

workflow :

    - Technology


---

# Realign resource assignments with demand

# Realign resource assignments with demand {#ariaid-title1}

* Release version: Zurich
* 
* Updated March 6, 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

Planning and execution of your roadmap involves change in priority or timelines of your work. In such cases, you can adjust the resource assignment dates to match with the latest dates of your demands.

## Before you begin

[Migrate resource plans to resource assignments](https://www.servicenow.com/docs/jYtl8MEUMJl2aVKZ8hBstQ "Migrate resource plans and cost plans of your projects or demands to resource assignments and attribute-based cost plans. Then, work on the resource allocations and project financials using Project Workspace.")

Role required: it_demand_manager

## Procedure

1. Navigate to AllDemandDemandsAll.
2. Open the required demand.
3. Change the Approved start date and Planned start date to meet your organizational priorities.
4. Select Save.
5. Select the Realign assignments to demand related link.

## Result

In the Resource assignments related list, you can see the Start date of the resource assignments aligned with the demand start dates.

*[\>]: and then


