Project field mapping
During an import, values from Microsoft Project overwrite fields in project records.
| Microsoft Project fields | Project Management fields |
|---|---|
| Task Name | Short description. The field is overwritten only while you import the first time. |
| Note | Description |
| Start | Planned start date |
| Finish | Planned end date |
| Duration | Planned duration |
| Actual Start | Actual start date |
| Actual Finish | Actual end date |
| Actual Duration | Actual duration |
| % Complete | Percent complete (personalize the form to add this field) |
| Predecessor Lag | Lag time between predecessor and successor |
| WBS | WBS |
| Critical | Critical path |
| Rollup | Rollup |
| Text10 (Field used for syncing purposes) | Task Sys_Id |
| Project Header Title | Project name |
| Project Header Subject (Field used for syncing purposes) | Top Task Sys_Id |
| Resource | Assigned to [assigned_to] Note: During import, if there are multiple resources
assigned to a task in Microsoft Project:
|
| Resource Group | Assignment Group |