# Migrate operational resource plans

# Migrate operational resource plans {#ariaid-title1}

* Release version: Zurich
* 
* Updated July 31, 2025
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

Migrate the required Operational resource plans to attribute-based Operational resource assignments.

## Before you begin

Role required: resource_manager, it_project_manager, demand_manager, admin

## Procedure

1. Navigate to AllResourceResource PlansAll Operational Plans.
2. Select the list of operational resource plans to migrate.
3. Select Migrate resource plans from the Actions on selected rows... list.  
   Operational resource plans are migrated to Operational resource assignments. You can view the list of Operational resource assignments at AllResourceResource AssignmentOperational Resource Assignments.  
   Tip:  
   You can [Scheduled job to migrate resource plans and cost plans](https://www.servicenow.com/docs/XrfoVmRfQJYJZEnW77D6Lg "Activate the Migrate Resource Plans scheduled job to migrate resource plans, operational resource plans, and cost plans of your projects and demands. This job converts them to resource assignments and attribute-based cost plans.").

*[\>]: and then