Associate a time card with a resource plan

  • Release version: Zurich
  • Updated July 31, 2025
  • 1 minute to read
  • If one resource is allocated to identically named tasks in two resource plans, use the following procedure to specify the resource plan the time card should be allocated to.

    Before you begin

    Role required: resource_manager

    About this task

    • A resource plan can be associated with a time card only if the resource plan contains hard allocations for the user.
    • If a resource plan isn’t associated manually to a time card, then a resource plan is auto-associated. The auto-association is done based on the selected Task in the time card.

    Procedure

    1. Navigate to the All > Time Cards > All.
    2. Select a time card.
    3. Configure the form to add the Resource plan field.
    4. In the Resource plan field, select the plan to which the time card should be allocated.
      Only resource plans that contain the selected task are listed.
      Figure 1. Time Card with Resource Plan
      Screenshot for a time card configured with Resource Plan
    5. Select Update.