# Reviewing progress status for SAFe features and epics

# Reviewing progress status for SAFe features and epics {#ariaid-title1}

* Release version: Zurich
* 
* Updated March 12, 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

Understand if your work would be completed by the planned end dates by reviewing
progress status of your SAFe features and epics.

Navigate to Scaled Agile Framework (SAFe)Epics or Scaled Agile Framework (SAFe)Features and filter the records for your team.  
The Status column of the list shows a Green, Yellow, or Red indicator for each record to indicate the following:

* Green: Your work is on track to be complete by the planned end date.
* Yellow: Your work is off track and your plan of execution must be reviewed.
* Red: Your epic or feature is not progressing well and might be at risk of not being complete by the planned end date.
{#review-safe-epic-feature-progress-status__ul_crv_nkz_4mb}

The estimated completion date displays a date with the likelihood of the epic's or feature's
completion.
Figure 1. SAFe epic progress status

The [\[SAFe\]
daily data collection job](s9I0KwrzL28SSyoreEXyzg "Enable scheduled data collection to begin collecting scores on new data automatically for Essential SAFe dashboards. Data collection jobs automatically collect scores for automated indicators and breakdowns.") helps generate the burnup report for your epics and features.
Using the data generated for these epic burnup reports, an estimated completion date is
determined. You can see that this date is the intersection of Completed and Scope forecast series
in the respective burnup reports.  
Based on this estimated completion date, the progress status for your SAFe epics and features is determined. Progress status is calculated only under the following conditions:

* Planned end date is populated for the SAFe epic and feature.
* Percentage completion of the epic is a value greater than 0.
{#review-safe-epic-feature-progress-status__ul_ohf_pjz_4mb}  
The color of the progress status indicator is determined using the following conditions:

* Green: Estimated completion date is on or before the planned end date.
* Yellow: Estimated completion date is beyond the planned end date by a deviation of 1% to 14%.
* Red: Estimated completion date is beyond the planned end date by a deviation of 15% or more.
{#review-safe-epic-feature-progress-status__ul_dg1_llz_4mb}
**Related concepts**   

* [SAFe Feature Dashboard](https://www.servicenow.com/docs/hdGWftkmdctDJuoA~up7KQ "The SAFe Feature Dashboard provides a visualization of the changes in scope and the progress of the stories in the feature over a given period.")
* [SAFe Epic Dashboard](https://www.servicenow.com/docs/uCjcpQ21tASWwjzGVfbRNQ "The SAFe Epic Dashboard provides a visualization of how the features of an epic are progressing over a given period of time.")

*[\>]: and then