Maintenance schedules are executed whenever the meter, duration, script, or condition
criteria is met. You can also use the Schedule ad-hoc feature to run a maintenance schedule
manually.
Before you begin
Role required: SM admin
About this task
Maintenance schedules are run regularly using the Planned Maintenance
Nightly Run scheduled job. When the scheduled job is run, the
appropriate Service Orders are created for all records that meet the schedule
criteria (including all records for the current day).
To configure the nightly planned maintenance scheduled job:
Procedure
-
Navigate to .
-
Open Planned Maintenance Nightly Run.
-
In Related Links, click Configure Job Definition.
-
To specify a different schedule for running the job, change the
Run and Time fields.
A scheduled job does not run based on the value set in the
Next run
time field in the maintenance plan record for this job. For more
information, see
Configure a maintenance schedule.
-
Click Update.
-
At any time, to run the scheduled job, click Execute Now.
The scheduled job evaluates all previously defined schedules and executes the ones that are scheduled to run.
Note: If one or more records in the table associated with the maintenance plan are deleted after the matching records were associated with the maintenance plan, the next nightly run removes all the records
associated with those removed assets.