Create a parent-child relationship on the planning console

  • Rversion finale: Australia
  • Mis à jour 12 mars 2026
  • 1 minute de lecture
  • The WBS section of the planning console allows you to create parent-child relationships for new tasks or move around existing tasks in a new parent-child relationship. The position of a task in the hierarchy and the level of indentation determine the parent-child relationship it has with the tasks above or below it.

    Avant de commencer

    Role required: it_project_manager

    Pourquoi et quand exécuter cette tâche

    In this example, the System Readiness Assessment task is a child of the Planning task because it is one level below the Planning task and is indented.
    Figure 1. Parent-child relation for tasks
    Parent-child task example

    Procédure

    1. Select a task in the WBS section of the planning console to highlight it.
    2. Select a combination of any of the following icons to create the task and move it or move the other tasks to create the required hierarchy:
      Tableau 1. Creating parent-child relationships
      Icon Action
      Add task above icon (Add task icon) Create a task above the highlighted task.
      Add task below icon (Add task icon) Create a task below the highlighted task.
      Indent icon (Indent icon) Makes the highlighted task a child of the task above it.