Create a dependency from the planning console

  • Rversion finale: Australia
  • Mis à jour 12 mars 2026
  • 1 minute de lecture
  • Create a dependency between two tasks on the planning console.

    Avant de commencer

    Role required: it_project_manager

    Pourquoi et quand exécuter cette tâche

    You can create any type of dependency. See Parent-child rollup task calculations for an explanation of each type.

    You can also create dependencies by using the Predecessor column on the Planning Console. See Predecessor dependencies in the planning console for more information.

    Procédure

    1. Select a task on the Gantt chart portion of the planning console.
      A white circle appears on either end of the task, one at the start of the task and the other at the end of the task.
    2. To create a dependency, select one of the white circles and drag it to the start or end of another task.
    3. Double-click the dependency line to see the dependency on the Planned Task Relationship form.
    4. Confirm that your dependency is correct.