Create a milestone

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:1分
  • A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones.

    始める前に

    Role required: it_project_manager

    このタスクについて

    注:
    Milestones cannot be shared between projects unless one project is nested under another project.

    手順

    1. Create a project task and give the Duration field a value of 0.
    2. Open the planning console Gantt chart and verify that it appears as a diamond.
      You can also convert a task to milestone through Planning console tasks.

    タスクの結果

    図 : 1. Milestone
    Milestone example