Nitesh Alashe1
Giga Expert

I have tested Conflict for these schedules which are Blackout and Maintenance

  • Only Maintenance Schedule is Active on: Monday, Tuesday, and Wednesday

Planned Start Date

Planned End Date

Results

Friday

Monday

Maintenance Schedule Conflict

Monday

Wednesday

No Conflict

Monday

Friday

Maintenance Schedule Conflict

 

  • Only Blackout Schedule is Active on: Wednesday, Thursday

Planned Start Date

Planned End Date

Results

Monday

Wednesday

Blackout Schedule Conflict

Wednesday

Thursday

Blackout Schedule Conflict

Wednesday

Friday

Blackout Schedule Conflict

Tuesday

On Same Tuesday

No Conflict

Friday

On Same Friday

No Conflict

 

  • Both Maintenance and Blackout Schedule are Active
  • Maintenance Schedule: Monday, Tuesday, Wednesday
  • Blackout Schedule: Wednesday, Thursday

Planned Start Date

Planned End Date

Results

Monday

Wednesday

Blackout Schedule Conflict

Friday

Tuesday

Maintenance Schedule Conflict

Tuesday

Friday

Blackout Schedule Conflict

 

Maintenance Schedule Conflict

Friday

Friday

Blackout Schedule Conflict

 

Maintenance Schedule Conflict

Friday

On Same Friday

Maintenance Schedule Conflict

Monday

Tuesday

No Conflict

Friday

Wednesday

Blackout Schedule Conflict

 

Maintenance Schedule Conflict

Thursday

Thursday

Blackout Schedule Conflict

 

Maintenance Schedule Conflict

Tuesday

Wednesday

Blackout Schedule Conflict

Wednesday

Wednesday

Blackout Schedule Conflict

Monday

Friday

Maintenance Schedule Conflict

 

 

 

*Note:            

If Change is planned outside Maintenance Window-->Maintenance Conflict

If Change is planned in Blackout than -->Blackout Conflict

If Change is planned to start in Maintenance Window but it ends outside Maintenance Window in which some are Blackout days--> Both the conflicts

 

 

 

Documented by 

-Nitesh

 

Please mark helpful if someone really feels its helpful.

Comments
Avant Kumar
Giga Contributor

I am unable to see the New option on Blackout Schedule form. I have change manager role. Is there any specific role that someone need to have to create New blackout schedules in ServiceNow?

Chaz_
Tera Guru

Hi Avant,

 

In order to create schedules, you will need either the 'schedule_admin' or 'itil_admin' role. I would suggest using the schedule_admin role, as it is more limited than the itil_admin role.

 

See doc link below showing the pre-requisite roles

 

https://docs.servicenow.com/bundle/vancouver-platform-administration/page/administer/time/task/creat...

 

Chaz.

 

Please mark the answer as helpful or as the correct answer to help others!