Hey Everyone
I have developed a functionality to include project's Expected Percent Complete on project which helps PMs to calculate the variance of Percent Complete.
This can be used on any version since this is completely custom and you will not have any problems during upgrades as well.
This can be done for single project through related link or multiple projects at once through list button.
The field Expected Percent Complete is = (No of task's planned end date is on or before today/total no. of tasks)*100
Project Form
Related Link
After clicking link
Project List view button (You can also apply filters to the list and it will calculate only to those projects)
after clicking button
after the update is complete
Hope this article is helpful to you guys.
Thanks and Regards
M. Ashwath Kumar Reddy