M Ashwath Kumar
Mega Expert

Hey Everyone

I have developed a functionality to include project's Expected Percent Complete on project which helps PMs to calculate the variance of Percent Complete.

This can be used on any version since this is completely custom and you will not have any problems during upgrades as well.

This can be done for single project through related link or multiple projects at once through list button.

The field Expected Percent Complete is = (No of task's planned end date is on or before today/total no. of tasks)*100

Project Form 

find_real_file.png

Related Link

find_real_file.png

After clicking link

find_real_file.png

 

Project List view button (You can also apply filters to the list and it will calculate only to those projects)

find_real_file.png

after clicking button

find_real_file.png

after the update is complete

find_real_file.png

Hope this article is helpful to you guys.

Thanks and Regards

M. Ashwath Kumar Reddy

 

 