Rajesh_Singh
Kilo Sage
Kilo Sage

This article is a quick reference to understand the calculation behind Project financials.

Below is a screenshot of the Financials section from Project/Demand

No alt text provided for this image

Total Planned Cost: It's the total estimated cost of the Project. In ServiceNow, it is just a sum of all cost plans items

Planned Capital: It's the cost of developing or procuring a product/service. In ServiceNow, it's the sum of all cost plans, where the cost type is 'Capex'.

Planned Operating: It's the ongoing cost for supporting day-to-day business/services. In ServiceNow, it's the sum of all cost plans, where the cost type is 'Opex'.

Budget Cost: A sum of money allocated for a project for a specific period of time. In ServiceNow, it's a sum of the budget allocated to Demand/Project in a given fiscal period.

Actual cost: It's the total cost of all accomplished tasks in a project. In ServiceNow, it's a sum of the 'Processed' expense line items.

Planned Benefit: It's the total estimated benefit from the Project. In ServiceNow, it's a sum of all benefit plans line items.

Planned Return: It's an estimation of financial gain (or loss) from a projectIn ServiceNow, it's calculated as "Total Planned cost - Planned Benefit".

Planned ROI %: Its profitability percentage of your project investment. In ServiceNow, it's calculated as (Planned Return/Total Planned cost)*100

Discount Rate %: It is an interest rate used to determine the present value of future cash flows. In ServiceNow, it's manual value input by Project Manager

Net Present Value: It is used to calculate the current value of all future cash flows generated by a project. In ServiceNow, it's calculated using the formula

NPV = Planned benefit/(1+i)^t

If the discount rate is 5% then the value of i will be 0.05, t = Number of time periods

Internal Rate of Return %: Basically one can measure IRR by calculating the interest rate at which the present value of future cash flows is equal to the capital required for the project. Generally speaking, the higher an investment's IRR, the more desirable it is to carry on with the project. IRR calculations rely on the same formula as NPV does. Keep in mind that IRR is not the actual dollar value of the project. It is the annual return that makes the NPV equal to zero.

0 = NPV = ∑(((Planned benefit/1+IRR)^t) - Total Planned cost)

However, it's not that easy to calculate IRR manually. instead must be calculated iteratively through trial and error.

However in Servicenow, for IRR to be populated, the following conditions must be met:

  1. Cost plan and/or benefit plan records should be present for at least two Fiscal years
  2. There should be at least one fiscal year with a positive value (Sum of benefit plan breakdown values for the fiscal period is greater than the sum of cost plan breakdown values)
  3. There should be at least one fiscal year with a negative value (Sum of cost plan breakdown values for the fiscal period is greater than the sum of benefit plan breakdown values)

The logic for the above is implemented in the Script Include - /nav_to.do?uri=sys_script_include.do?sys_id=c8fa147f0b372200a6acc93563673a40

For more information on NPV and IRR calculations in ServiceNow, please refer: Link

Estimate at Completion: Sum of all actuals for past fiscal periods added to the planned cost for future fiscal periods.

Example: To understand this, let's consider the example: You have a project duration from January to May. And you want to calculate EAC in March, then EAC = Actual cost (from Jan to Feb) + Planned cost of the remaining fiscal period (March to May)

No alt text provided for this image

Estimate to completion: Sum of all planned costs for future fiscal periods.

From the above example, ETC = Planned cost of the project for the remaining fiscal period (March to May).

Thank you for reading. Do let me know, what would be the next topic/concept you like to read.

#servicenow #ppm #itbm #projects #projectfinancials

Cheers!

Comments
vg47641
Tera Contributor

Nice one

Rajan kumar7
Tera Contributor
Very useful post .
Kunwar1
Tera Explorer

Thank you! for sharing

Kalpesh6
Mega Explorer

Thanks for explaining the cost and calculations using a graph. Made it more clear!

Ramakrishna Ch2
Mega Explorer
Useful
Rabindra kumar
Tera Explorer

You just light up me on this financial calculations...informative article.

Vivekanandan
Tera Contributor

Useful

Lici
Tera Contributor

I'm sorry about your financial situation. It's a far too complicated situation. I have never been in such a situation. It really would have been much more comfortable if she had lived with you or had a better-paid job. But is it not possible to send money by card or bank? There are various international transfers. If this solution doesn't work, to be honest, I have no idea. I am afraid to end up in such situations. I started my own business, and I'm afraid of doing the wrong thing financially. For this, I also use DCF Terminal Value Formula, which I found on wallstreetoasis.com, to make fixed money predictions for the coming years so that I have enough money for each month. I recommend you do the same. I hope that everything will be fine for you and find a way to transfer the money as soon as possible.

PG9
Tera Contributor

useful and concise

Dhiren Aghera
Tera Guru

Really helpful as a quick snippet as it sometimes difficult to remember. Thanks for putting these togather.

SANDEEP26
Mega Explorer

good one

Alpa82
Tera Expert

@Rajesh_Singhthank you very much for this overview.

Would you also know if there is any feature/field in SN that would be used for tracking the Weighted Average Cost of Capital (WACC) and compare the IRR x WACC?
thank you

Captain Gaming
Tera Contributor

Hi @Rajesh_Singh 
In my case, I couldn't find the Amount field while creating Expense lines. Can you help me understand how to populate the Total Actual cost in the Cost Plan?

Version history
Last update:
‎07-22-2021 10:35 PM
Updated by: