1. Purpose and audience

Now Assist for Strategic Portfolio Management (SPM) can prefill a project status report: it predicts a Red, Amber, or Green (RAG) status for four health dimensions, combines them into an Overall Health status, and writes an executive summary of the project.

 

Two roles shape the result. The administrator defines how health is judged. The project manager triggers the report and reviews the output. This article explains the feature from the perspective of each role.

This article focuses on what each role does rather than on individual metrics. The feature includes many more metrics, which are listed in Section 5.

 

Role Responsibilities in this feature
Administrator Writes the RAG criteria for each health dimension. Decides which analysis topics are active. Optionally overrides topic settings for a specific project.
Project manager Triggers AI-assisted status report generation. Reviews the health status for each dimension, the Overall Health status, and the executive summary.

 

2. The end-to-end flow

When a project manager triggers AI-assisted status report generation, the system runs six parallel evaluations: Schedule, Cost, Resource, Scope, Overall Health, and the Executive Summary. Each health evaluation follows the same five steps.

 

Step What happens Who influences it
1. Load active topics The system loads the analysis topics that are switched on for the dimension. Administrator
2. Extract project data Each topic reads the relevant project data, such as tasks, cost plans, resource assignments, or risks. Project manager (through the data kept in the project)
3. Classify findings Each topic applies its thresholds and produces structured insight text, for example a severity level. Product defaults; administrator for per-project overrides
4. Send to the LLM The insights are sent to the large language model (LLM) together with the administrator's RAG criteria. Administrator
5. Return health The LLM returns Red, Amber, or Green for the dimension. Project manager reviews the result

The topics classify and describe findings, but the LLM makes the Red, Amber, or Green decision by comparing those findings against the administrator's written criteria. The same project data can therefore produce different results under different criteria.

 

Analysis date range

Every topic works within a date window centered on today. The status report uses a weekly cadence by default: from seven days before today to seven days after today, snapped to Monday at the start and Sunday at the end. Tasks, milestones, and assignments that fall entirely outside this window are excluded.

 

3. The administrator journey

The administrator controls how health is judged: what the criteria say, which topics run, and whether a project needs different settings.

 

3.1 Configure RAG criteria for each dimension

RAG criteria are free-text instructions that tell the LLM how to classify Red, Amber, and Green. Each criteria field accepts up to 8,000 characters, and the text is sent to the LLM as written.

  1. Open the NowAssist Skill Config UI.
  2. Enter / Review the OOB criteria for Schedule, Cost, Resource, and Scope health. Enter criteria for Overall Health if the default rule is not suitable.

MahatmaK0342012_6-1795531533636.png

 

MahatmaK0342012_7-1795531542630.png

 

 

If criteria are not configured for a dimension, the behavior depends on the dimension.

Health dimension Config variable If not configured
Schedule schedule_health The section is skipped and listed under skipped sections
Cost cost_health The section is skipped and listed under skipped sections
Resource resources_health The section is skipped and listed under skipped sections
Scope scope_health The section is skipped and listed under skipped sections
Overall overall_health A built-in rule is used: any Red dimension gives Red, two or more Yellow give Yellow, otherwise Green

While enabling the skill, the administrator must therefore review the four OOB dimension criteria before project managers will see those AI sections in a report.

 

4. The project manager journey

The project manager triggers the report from project workspace and reviews what the system prefilled, in six steps.

  1. Trigger generation. The project manager starts AI-assisted status report generation for the project.
  2. Wait for the evaluations. The six evaluations run in parallel and prefill the report.
  3. Review each dimension. Schedule, Cost, Resource, and Scope each show a Red, Amber, or Green status based on the project data and the administrator's criteria.
  4. Review Overall Health. This status is derived from the four dimension statuses.
  5. Review the executive summary. This is a written narrative of the project's current state and trend.
  6. Check for missing sections. If a dimension is absent from the report, its RAG criteria have not been configured. The project manager contacts the administrator.

MahatmaK0342012_8-1795531562625.png

 

MahatmaK0342012_9-1795531572435.png

 

 

How the executive summary detects trends

The executive summary is a narrative rather than a status. The LLM compares two snapshots of the project: the current project record and the most recent previous status report. Fields compared include percent complete, schedule, phase, state, and the start and end dates. The difference between the two snapshots produces statements such as "percent complete increased from 45% to 62% since the last report."

MahatmaK0342012_10-1795531583679.png

 

The summary also uses overdue high-priority tasks, open risks, open issues, and active milestones in the date window.

Because the project manager's own data drives every result, accurate project data matters: baselines, cost plans, resource assignments, and up-to-date risks and issues.

 

5. Beyond these four metrics

This article covers one metric per dimension as a sample. Each dimension includes additional topics (Supported metrics) as well that work the same way: they read project data, classify findings, and pass insights to the LLM, which applies the administrator's criteria.

 

MahatmaK0342012_11-1795531605250.png

 

 

Dimension Metric supported Other available metrics (Admin can configure)
Schedule Schedule Variance Project Delay Issues; Scope Creep Issues; Missed Milestone Deadlines; Milestones with No Clear Ownership; Milestone Dependency Delays
Cost Cost Variance Issues Budget Variance Issues; Budget Fluctuation Issues
Resource Resource Overallocation Resource Underutilization; Unplanned Absence; Resource Unavailability; Contract Resource Issues; Available Users in Project; Resource Conflicts
Scope Open Risks Open Issues; Open Decisions; Open Actions; Open Change Requests

 

A detailed reference article below covers every topic, including the data fields read, the calculation, the severity thresholds, and the effective status report configuration.

 

6. Summary

  • The administrator defines (reviews OOB) how health is judged by writing RAG criteria for Schedule, Cost, Resource, and Scope, and optionally for Overall Health.
  • Dimensions without criteria are skipped. Overall Health is the only section with a built-in fallback.
  • Topics classify findings with thresholds, but the LLM decides Red, Amber, or Green by applying the administrator's criteria.
  • The project manager triggers generation, reviews each dimension, Overall Health, and the executive summary, and escalates missing sections to the administrator.
  • The executive summary identifies trends by comparing the current project record with the previous status report.
  • Accurate project data (baselines, cost plans, assignments, risks) directly improves the quality of the result.