The Project Data Quality Index checks each project against 20 rules and gives it a rating. This article lists every rule, what it checks and the condition behind it, so you can see why a project scored the way it did and what to fix.

 

How scoring works

  • Each rule is a pass or a fail, with no partial credit.
  • Rules sit in six dimensions. A dimension's pass rate is the share of its rules that pass.
  • Pass rates become a rating for each dimension and for the project overall.
  • The rules are checked the same way every time. AI then explains the results and suggests what to improve.

Pass rate

Rating

85% to 100%

Excellent

70% to 84%

Good

55% to 69%

Fair

35% to 54%

Poor

0% to 34%

Critical

 

These are the defaults. Your admin can change them.

The ID is a rule's internal number, not a count. There are 20 rules, and some numbers are unused.

 

Example: a project scored

Here is a fictional project, "Customer Portal Upgrade", with its data partly filled in. Rule IDs are in brackets.

 

Dimension

Rules passed

Failed rules

Pass rate

Rating

Project Charter

4 of 5

Business case is only 12 characters [3]

80%

Good

Schedule & Milestones

3 of 4

No milestone notes in 30 days [7]

75%

Good

Resources & Team

2 of 3

One unapproved assignment is past its start date [14]

67%

Fair

Scope & Financials

2 of 4

No expense lines [18], no monetary benefit plan [20]

50%

Poor

Reporting & Activity

3 of 3

None

100%

Excellent

RIDAC Coverage

1 of 1

None

100%

Excellent

 

Overall: 15 of 20 rules pass (75%). With the default dimension weights, the overall rating would most likely be Good. AI makes the final call, so a project near a boundary could land on either side.

 

The AI also explains each rating and suggests where to start. For example (wording is illustrative):

 

Scope & Financials: Poor. The project has a budget but no recorded spending, and no monetary benefit plan, so cost control and the expected return can't be tracked. Suggested first step: add expense lines to start tracking actuals, then create a monetary benefit plan.

Fixing rules 18 and 20 would move Scope & Financials from 50% to 100% and lift the overall rating.

 

Project Charter

ID

Rule

Passes when

Technical condition

1

Name is descriptive

The name is at least 10 characters and isn't a placeholder.

short_description length ≥ 10 and not Project 1, New Project, Test, Untitled, TBD or New.

2

Description populated

The description is at least 20 characters.

description length ≥ 20.

3

Business case filled

The business case has at least 30 characters.

business_case length ≥ 30, HTML removed.

4

Investment type and class set

Both are filled in.

investment_type and investment_class not empty.

5

Scope description filled

The in-scope description has at least 10 words.

in_scope word count ≥ 10, HTML removed.

 

Schedule & Milestones

ID

Rule

Passes when

Technical condition

7

Milestone notes updated within 30 days

A milestone has a note from the last 30 days.

A sys_journal_field entry in the last 30 days on a milestone (pm_project_task, milestone = true). Fails if there are no milestones.

8

Project baseline exists

The project has a baseline.

A planned_task_baseline_item exists for the project.

9

Active milestones have owner

Every unfinished milestone has an owner.

Each milestone with work_end empty has assigned_to or assignment_group. Fails if there are none.

10

Project manager assigned

A project manager is set.

project_manager not empty.

 

Resources & Team

ID

Rule

Passes when

Technical condition

11

Active named resource assignment with future end date

A named person is assigned and the assignment hasn't ended.

A resource assignment with assignment_type = user and end_date today or later.

14

Unapproved stale resource assignments

No assignment is both unapproved and past its dates.

No assignment with resource_status ≠ approved and start_date or end_date before today.

15

Contractors have employment end date

Every contractor has an end date on their profile.

Each external assignment's profile has employment_end_date. Passes if there are none.

 

Scope & Financials

ID

Rule

Passes when

Technical condition

16

Approved budget set

The budget is greater than zero.

budget_cost > 0.

18

Actuals tracking started

There is a budget and an expense line.

budget_cost > 0 and an fm_expense_line exists for the project.

19

Labor cost plan exists

The project has a labor cost plan.

A cost_plan exists with resource_type.name containing "Labor".

20

Monetary benefit plan exists

The project has a monetary benefit plan.

A benefit_plan exists with benefit_type = monetary.

 

Reporting & Activity

ID

Rule

Passes when

Technical condition

22

Status report created within 30 days

A status report was created in the last 30 days.

A project_status record for the project with sys_created_on in the last 30 days.

24

Record actively maintained

The project was updated in the last 30 days.

sys_updated_on within the last 30 days.

25

Notes or comments added recently

A note was added in the last 30 days on the project or related items.

A sys_journal_field entry in the last 30 days on the project, its tasks, risks, issues, decisions, actions or change requests.

 

RIDAC Coverage

RIDAC stands for risks, issues, decisions, actions and change requests.

ID

Rule

Passes when

Technical condition

26

At least one RIDAC item exists

The project has any one of those items.

A risk, issue, dmn_decision, project_action or project_change_request record exists for the project.

 

Point to Note

  • After the rules run, AI explains each dimension’s rating in plain language, so you can see why a project scored the way it did. It also recommends what to fix first, starting with the failed rules that matter most.
  • Small dimensions swing more. RIDAC has one rule, so it scores 0% or 100%. Each Charter rule is worth 20%.
  • Nothing there often means a fail. Milestone, baseline and plan rules fail until a record exists. The contractor rule passes if the project has no contractors.
  • Defaults can be changed. Your organization can add, change or turn off rules, so your scores may differ from the defaults described here. See the customization article for how.  Tailor the Project Data Quality Index to your process: add, change and turn off rules