5 hours ago
Q: Why is the export action not working?
A:
- Review your custom map configuration.
- Ensure the custom field is added to the default screen scheme of the issue.
- Make sure the Enable Export checkbox is selected in the project integration settings for this Jira project or board.
- Check if your Jira password has expired.
Q: Why is a sprint not associated with imported stories?
A:
- Verify if the sprint is started in Jira.
- If the sprint is a future sprint, it will not be associated with stories in Agile Development.
- Sprint data from Jira is updated in Agile Development only if the sprint is active in Jira.
Q: Why is a sprint not imported into Agile Development 2.0?
A:
- Ensure your sprint in Jira has dates.
- Make sure sprint dates in Jira do not overlap with another sprint in the same assignment group in Agile Development 2.0.
Q: Why is a value from a field in Jira not populated in Agile Development 2.0?
A:
- Verify if the custom field map is configured.
Q: Why are the Priority or State fields from Jira not populated in Agile Development 2.0?
A:
- Check if the custom workflow state map is configured.
Q: Why is an update by a user in Jira not updated in Agile Development 2.0?
A:
- Ensure the user credentials used to set up the integration are not used to perform record updates.
Q: Why is an issue deleted in Jira not deleted in Agile Development 2.0?
A:
- Make sure the Can Delete field in Application access of the relevant tables is set to true.
Q: Why do I see duplicate comments when importing from Jira Cloud?
A:
- Verify the cyclic payload.
- Ensure privacy settings are enabled for the connection user (used in HTTP connection in Agile Development 2.0).
Q: Why is the email address visible in webhook events?
A:
- Review webhook configuration and privacy settings.
Q: Why does deleting a project or board in Jira not result in any action in Agile Development 2.0?
A:
- After deleting the project or board in Jira, the Jira administrator must manually delete the associated stories in Agile Development 2.0.
Q: Why does using rich text in Jira result in garbled text in Agile Development 2.0?
A:
- The wiki text format used in Jira is not supported in Agile Development 2.0.
Q: Why is the relation between story and epic not imported for a Next-gen Jira project?
A:
- In Jira, make a nominal update to the story to send the epic relation along with this update to Agile Development 2.0.
Q: Why are sub-tasks not imported or exported between Jira and Agile Development 2.0?
A:
- To enable import of sub-tasks from Jira to Agile Development 2.0, manually configure custom mapping for this task type.
- https://www.servicenow.com/docs/bundle/zurich-it-business-management/page/product/agile-jira-integra...
Q: Why are scrum tasks not exported from Agile Development 2.0 to Jira for a Next-gen Jira project?
A:
- Only import of sub-tasks from Jira to Agile Development 2.0 is supported, not export.
Q: Why is map configuration not generated for a project after importing projects?
A:
- Ensure the user for whom the connection alias is created has access to all Jira projects.
Q: Why do UI actions for Connect, Disconnect, and Validate and Fix result in an error when used for the first time?
A:
- This is a known issue. Retry the UI action.
Q: Why does the API call fail in Flow Designer with an “API response size exceeded” error while fetching Jira project metadata?
A:
- Reduce the batch size property by setting it to a value between 1 and 50.
- https://www.servicenow.com/docs/bundle/zurich-it-business-management/page/product/agile-jira-integra...
Q: Why are import issues staying in 'Processing' state forever?
A:
- Import requests may be stuck if the server type is incorrectly set as 'cloud' instead of 'server'.
- Set guidelines for Jira on-prem customers to use proper connection attributes.
Q: Why does bulk importing of work items data fail with an “API response size exceeded” error?
A:
- Reduce the value of MAX_LIMIT in the JiraConstants Script Include and try to bulk import again.
Q: How can I enable detailed project logs for troubleshooting?
A:
- Enable the integration project logging property.
- https://www.servicenow.com/docs/bundle/zurich-it-business-management/page/product/agile-jira-integra...
Enabling Detailed Project Logs
To view detailed logs, enable the integration project logging property.
See how to enable detailed logging in Jira Integration with Agile Development.