We are looking for some guidance to better understand the Actual Start Date and Actual End Date fields in Strategic Planning Workspace. We would like to know what exactly sets the Actual Start Date and Actual End Date fields and how these two fields affect the Planned Start/End Date and Approved Start/End Date for Planning Items (e.g., Epic and Feature).
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
a week ago
Hi @juliebailey
Refer: Project planning item form
Field Description
| Planned start date | Date on which the work for this planning item is planned to start. This value is copied from the Approved start date field. |
| Planned end date | Date on which the work for this planning item is planned to be complete. This value is copied from the Approved end date field. |
| Approved start date | Approved start date for this planning item. |
| Approved end date | Approved end date for this planning item. |
| Actual start date | Actual date on which the work for this planning item has started. |
| Actual end date | Actual date on which the work for this planning item is complete. |
Also check: https://www.servicenow.com/docs/r/it-business-management/scenario-planning-in-spw/initiative-form.ht...
Regards
Tanushree Maiti
ServiceNow Technical Architect
LinkedIn: https://www.linkedin.com/in/tanushreemaiti
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
a week ago - last edited a week ago
Hi @Tanushree Maiti,
Thank you for your quick response. This summary is helpful. Do you by chance know what sets the Actual Start/End Dates? They are grayed and we are unsure what actions sets the value to those fields.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
a week ago
Hi @juliebailey
Check these internal components /scripts which populate Actual Start/End Dates .
https://www.servicenow.com/community/spm-forum/project-task-actual-end-date/m-p/994232
https://www.servicenow.com/community/spm-forum/setting-actual-start-and-end-date/td-p/3390893
Regards
Tanushree Maiti
ServiceNow Technical Architect
LinkedIn: https://www.linkedin.com/in/tanushreemaiti
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
a week ago
Hi @juliebailey the Actual Start/End Date fields are execution fields and cannot be modified in SPW by portfolio user on Portfolio planning items. They are synced from the respective projects based on the update on the tasks status under the project. For ex: When all the tasks are marked complete in a project, the actual end date is populated.