Cost Plans created in Project Template defaulting to CAPEX Expense Type even when specified as OPEX

iromero
Giga Contributor

We are running on Zurich release. New to SNow SPM. We are finding that cost plans created in our template project plan, once saved as template and applied, bring all the cost plans over as CAPEX although they were created and saved as OPEX.

 

We may have found a fix to the issue when applying the template by going to the actual project template and then updating the four cost plans created to OPEX. Created a test project and applied said template and the cost plans now apply as OPEX. Not sure if there is some default value that is not allowing the template to maintain the OPEX setting when a project is saved as template.

0 REPLIES 0