How to link a subproject to an existing project within the project workspace

WataruS
Tera Contributor

I would like to know how to link a subproject to an existing project within the project workspace.

I understand that I can link them by selecting the subproject tab from the following screen and creating a new one, but is it not possible to link them directly within the project workspace?

WataruS_0-1758862834809.png

 

7 REPLIES 7

Hi @WataruS ,

 

Yes, Action exclusions basically exclude/hide button on the defined tables. So, if you remove it from the list it will show up in the related list. Test this is lower environments before making any changes to prod.

 

If my response helped you mark the solution as correct and close this thread.

 

Thanks

Anand

Hi, @ Anand2799 

Thank you for confirming.

I could understand.

However, even when I select “delete,” it won't disappear. Do I need some kind of special permission?

Hi @WataruS ,

 

Check if "Planned task" or "Task" table is added to exclusion list with Exclude all child tables=true.

I have tried by adding and removing pm_project to the list and it works for me as expected