Managing resources in the new Resource Management Workspace
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
- Labels:
-
Resource Management
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hiya,
My advice is to edit the actual Resource Assignments for the specific periods that a resource is needed, as they provide more flexibility than Resource Plans and don't get "locked" as RP used to.
In relation to your examples:
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Thank you so much for your response.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Tuesday
Hello again,
I instructed our PMs to change the end date, but it's forcing them to "Sync" the resources and it's realigning the resource dates with the project end date, which is completely incorrect. Resources on projects aren't always needed for the entirety of the project - they might be needed in the beginning or for a short period of time somewhere during the project. We are now having a difficult time managing resources accurately. Any additional guidance is appreciated. Thank you.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Wednesday
Hello EWood,
Changing the end date of the project task will require either a manual or (recently added) automatic resource sync. This is to ensure that the dates of a resource assignment are not outside the dates of the task. A simple example would be a decision to shift a project task to start in November instead of October. We want to 'sync' the assignments so that the resource assignments on that task move from October to November.
When you change the end date of a project task to be later than planned, we will not modify any assignments on that task by default (even when you hit sync). The sync is impacting any resource assignments on other tasks that were moved to the right due to task dependencies (see previous example).
When you change the end date of a project task to be sooner than planned (say, ending Sept 15 instead of Sept 30), any assignments on the project task are truncated to end Sept 15. If you have FS constraints and dependent project tasks shift left, resource assignments on those tasks will also shift left when the sync occurs.
There is a plan to release explicit 'end assignment early' functionality this October. The goal is to reduce clicks while letting you also modify resource states. We will also be merging (date tbd) the extend assignment functionality with the end early functionality so that you have a single place to make both changes.
I hope this helps,
Chris