Hello!
In our firm we use the PPM module for our Projects. In the projects we use the Planned vs Actual effort to keep up on the hours spent in the projects.
The problem is the days is setup as a 24 day, not 8 hour workday as it should be in our case. For example, if it is planned to use 25 hours in the project and I input this in the "Hours" field, it automatically autofills to 1 day(24h) and 1 hour instead of 3(8h x 3d) days and 1 hours.
We tried in our team to use the Project Management Schedule and this guide here from the forum: Project Management Schedule - explanation on the d... - ServiceNow Community
but we could not get it working, and I am not even sure it would change anything.
I hope someone knows the answer 😄
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-02-2025 06:27 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-02-2025 06:44 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-02-2025 06:29 AM
that's how the duration field will work.
It will convert hours to Days Hour Mins and Seconds automatically
If my response helped please mark it correct and close the thread so that it benefits future readers.
Ankur
✨ Certified Technical Architect || ✨ 9x ServiceNow MVP || ✨ ServiceNow Community Leader
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-27-2025 10:19 AM
I am struggling with this issue too. I use planned task on enhancements form and it changes hours to 24 hours day format. We want to keep it as hours or change it to 8 hours day format instead.