I have created a new custom field in pm_project table, customer want this field to be displayed in SPW as well and hence needs to be synced with sn_core_planning_item table or sn_core_planning_project. Is there any way to achive this without writing any custom business rules or script includes? To be more clear how already existing fields are mapped in both tables?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12 hours ago
Hi Shreya,
Are you doing everything via SPW, as in creating the new projects there or still using the PPM functionality? If the later, then I assume you've integrated it with SPW, in that case you will need to do the following:
- create the same field, with the exact same properties on the sn_align_core_project table
- use Table Map to create the connection between the 2 fields as per the screen shot
Hope this helps 🙂