Project baseline not appearing in Planning console (classic) but not in new Project workspace

CoolP
Tera Contributor

Freshly created baseline renders in Planning Console (Classic) but not in new Project Workspace — clean MS Project re-import, so not an ID sync issue

Environment: SPM Pro, [Zurich — glide-zurich-07-01-2025_patch7a-03-24-2026]

 

We have a project where the baseline displays correctly in the Classic Planning Console (grey baseline bars + Baseline Start/End/Variance) but does not render at all in the new Project Workspace Gantt.

Important detail: this is NOT a stale-reference situation. The team's process is to delete ALL tasks and ALL baselines, then re-import the MS Project schedule from scratch and create a new baseline. So the baseline is always captured fresh against freshly imported tasks — the task sys_ids and the baseline item references should be fully in sync. That rules out the usual "re-import orphaned the old baseline" explanation.

So the question is: with a clean rebuild, why would a brand-new baseline show in Classic but not in the new Workspace?

What we found while researching: PRB1456826 / KB0964588 ("Planning Console Baseline Errors") describes the baseline failing to render with the browser console error TypeError: Cannot set property 'baseline_start_date' of undefined, caused by records that are NOT Project Tasks/Projects (e.g. Requirements, Decisions) sitting in the Schedule Baselines related list. The workaround is to delete those non-task baseline items. This mechanism wouldn't depend on ID sync at all — a single non-task row in a freshly created baseline could break the Workspace render while Classic tolerates it.