Hi All --
We (I) am in need of updating cost plans created from an allocated resource plan after updating the rate in the Cost properties. I've read that the cost plans will not automatically be updated and we must execute the Update Cost Plan action each time to refresh the calculations.
I am having issue with understanding how to execute this Update Cost Plan action. We are currently on Yokahama 10b. Any guidance/experience is greatly appreciated.
TIA
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
5 hours ago
I am not familiar with Yokohama. In Zurich (New Experience) you go to the Financials tab and click on Generate Labor Costs.